* Put a report here | * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]] * Pre-isolator: The top filter was mounted onto the IP. The shaft screw of motor was not matching to the slider for fishing rod. New shafts were ordered. * EQ stop, release sensor, dummy payload: Production is on going. * BF damper: Open bidding is on 9th November. * Maraging wire: Hirata-san made 2D drawings. The wires will be ordered soon. * Installation: Making assembly drawings for the installation procedure document. The review is held on 4th November. |
Agenda/Minutes of the VIS Meeting on 2016/10/28
2016/10/28 13:30 - @Mitaka F2F.
Participants:
Progress report
Type-A (Takahashi)
- Pre-isolator: The top filter was mounted onto the IP. The shaft screw of motor was not matching to the slider for fishing rod. New shafts were ordered.
- EQ stop, release sensor, dummy payload: Production is on going.
- BF damper: Open bidding is on 9th November.
- Maraging wire: Hirata-san made 2D drawings. The wires will be ordered soon.
- Installation: Making assembly drawings for the installation procedure document. The review is held on 4th November.
Type B (Mark)
- Type B Past Week Summary
- Fabian, Mark and Liu-kun did BS installation at Kamioka:
- Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes.
- Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san.
- Removed IM trim mass to set the average height of the keystone to the CAD value.
- Moved IM trim mass around to set the pitch of the dummy BS.
- Hirata-san
- TBD.
- Fabian, Mark and Liu-kun did BS installation at Kamioka:
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Any issue ?
Discussion
- Suspension naming convention (Okutomi)
- Type-Bp installation tool: Lever block or Chain block (Shoda)
Site work plan for the next week
- Mon: BS test hanging
- Tue: BS test hanging
- Wed: BS test hanging
- Thu: BS test hanging
- Fri: BS test hanging
Travel Plans
- Travel (Week of 10/31):
- Takahashi:
- Shoda: 10/31 - 11/4? (PR3 disassemble)
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Ohishi:
- Travel (Week of 11/7):
- Takahashi: 7-9 (Extended chief meeting/Fire drill/Accelerometer test)
- Shoda: 7-11 (Extended chief meeting/Fire drill/PR3 disassemble)
- Mark: 8 - 11 (Fire drill/BS)
- Fabian:
- Okutomi: 7 - 11 (Extended chief meeting/Fire drill/Accelerometer test/Realtime code)
- Fujii: 8? (Fire drill)
- Ishizaki: 7-8? (Extended chief meeting/Fire drill)
- Hirata: 8? (Fire drill)
- Sato: 7-9 (Fire drill/Accelerometer test)
- Ohishi:
Next meeting
On 2016/11/4(Fri) VIS F2F: Nov. 18, Dec. 2