Agenda/Minutes of the VIS Meeting on 2016/11/25
2016/11/25 13:30 -
Participants:
Progress report
Schedule Chart (PDF,MPP) To Be Updated
Type-A (Takahashi)
- Put a report here
Type B (Mark)
- Put a report here
Type-Bp (Shoda)
- Put a report here
IMMT (Ohishi)
- Put a report here
Watchdog system (Tanaka)
- Put a report here
Safety
- Incidents
- Foreseen risks
Discussion
- PR3 accident: future actions
- Two ideas for improvement
- Making the long rods shorter
- For the disassembly, fix the mirror in the RM first, then open it and move the mirror to the mirror box.
- Status of consideration (Shoda, Takahashi, Hirata)
- Two ideas for improvement
Site work plan for the next week
- Mon:
- Tue: Power outage preparation/recovery (Aso)
- Wed:
- Thu:
- Fri:
Travel Plans
- Travel (Week of 11/28):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki: 12/1-2 (receive PI)
- Hirata:
- Sato:
- Enzo:
- Ohishi:
- Travel (Week of 12/5):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Ohishi:
All the teams should update the schedule from Dec. by the next meeting, so that the above travel plans become more realistic.
Next meeting
On 2016/12/2(Fri) F2F in Mitaka