 * Put a report here  * [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/TypeA/Meeting|Minutes of Type-A Meeting]]
 * Transportation: The pre-isolator and the GAS filters were transported to the 2nd floor of Y-end on 7-8th successfully. The second transportation is scheduled on 10-11th in January.
 * Pre-isolator: The assembly of pre-isolators for SR was started in ATC.
 * EQ stop, release sensor, dummy payload: The parts remained will be delivered on 12th.
 * BF damper: The production is on going.
 * Maraging wire: The production is on going.
 * Tooling for installation: The support frame for the PI was ordered. Investigating a fiber scope.

Agenda/Minutes of the VIS Meeting on 2016/12/9

2016/12/9 13:30 -

Participants:

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Transportation: The pre-isolator and the GAS filters were transported to the 2nd floor of Y-end on 7-8th successfully. The second transportation is scheduled on 10-11th in January.
  • Pre-isolator: The assembly of pre-isolators for SR was started in ATC.
  • EQ stop, release sensor, dummy payload: The parts remained will be delivered on 12th.
  • BF damper: The production is on going.
  • Maraging wire: The production is on going.
  • Tooling for installation: The support frame for the PI was ordered. Investigating a fiber scope.

Type B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Put a report here

IMMT (Ohishi)

  • Put a report here

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Incidents:
  • Foreseen risks:

Discussion

  • Mirror box modification status (Shoda)

Site work plan for the next week

  • Mon: BS/PR3 assembly frame
  • Tue: BS/PR3 assembly frame
  • Wed: BS
  • Thu: BS
  • Fri: BS

Travel Plans

  • Travel (Week of 12/12):
    • Takahashi:
    • Shoda: 12/12-13 Assembly frame, 12/15 or 16 (Kashiwa)
    • Mark: 12/12-12/16 (depending on BS vs SRx progress)
    • Fabian: 12/12-12/16
    • Okutomi:
    • Fujii: 12/15 or 16 (Kashiwa)
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo: 12/12-12/16 (for Type B )
    • Ohishi:
  • Travel (Week of 12/19):
    • Takahashi: 19-23 (Ext. Cheif Meeting/PI install)
    • Shoda: 19-23 (Ext. Cheif Meeting/PR3 test hanging)
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki: 19-23 (PI install)
    • Hirata:
    • Sato:
    • Enzo: 20-23 (PR3 test hanging)
    • Ohishi:

Next meeting

On 2016/12/16(Fri)