Line 12: Line 12:
Installation in Y-end:  Installation in Y-end:
Line 39: Line 40:
Line 40: Line 42:
 * Checked the optical bench suspension parts
  * Optical bench magnetic damper is in Akeno, delivered on Feb. 27th.
  * Jigs to arrange magnets on the optical bench magnetic damper is not designed nor procured.
  * Diameter of the head of the suspension rods are different from what we ordered. -> Asking company to make the correct ones.
  * Hooking screws cannot go smoothly even they are SDC coated. -> Asking to make the new ones loosely.
  * Cu plates for eddy current damping are oxidized so much. They do not look clean. just covered by bubble packs.

 * Assembled the whole stages
  * Not suspended yet.
  * Found the holes for suspension rods are too small. The company made a mistake on the drawing update.
   Two plates at Kamioka will be sent to the company. The other plate was re-machined at Mitaka.
  * Cabling around BF takes a lot of time...

 * BF LVDT temporally circuits were made by Miyo-kun, Someya-san, and Hashimoto-san.

 * Second test assembly of BFRM at Mitaka
  * ATC re-machined the holes for suspension rods. -> Will be sent to Kamioka.
  * BFRM was properly suspended.
Line 41: Line 62:
 * Suspend BF & BFRM
  * Adjust weight of the BF
  * place the ballast masses and balance it
  * Set LVDT coils on BFRM and check signals

 * Traverser parts will be replaced by Uraguchi-san

==== Long term to do ====
 * Calibration of BF LVDT
 * Check acceleration during the installation using the chain-block and jacks

Agenda/Minutes of the VIS Meeting on 2017/2/17

2017/2/17 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

Type-A (Takahashi)

Past week report

Installation in Y-end:

13th(Mon)

  • Installed the protection net to the bottom of cross tube.
  • Released the keystone of BF. The weight of dummy payload was near the optimal load of BF.

14th(Tue)

  • Tuned the weight of dummy payload.
  • Started cabling around the BF and the dummy payload. Finished on 16th.

15th(Wed)

  • Started making the short cable for the LVDT on BF. Not finished.
  • Prepared the LVDT driver with the oscillator and the oscilloscope.

16th(Thu)

  • Cariblated the LVDT on BF.
  • Checked the range of FR on BF. It was about 2mm. Additional blades are necessary.

MISC

  • The setup of EQ stop for prototype test was withdrawn from ATC on 17th.
  • Maraging wire: The 3.3m wire will be treated at Himeji facility of Kinzoku-giken. It takes one month.

Plan for coming weeks

  • Adjust the BF.
  • Assemble the BF damper.
  • Assemble the EQ stop for F3 and set the F3.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

  • Checked the optical bench suspension parts
    • Optical bench magnetic damper is in Akeno, delivered on Feb. 27th.
    • Jigs to arrange magnets on the optical bench magnetic damper is not designed nor procured.
    • Diameter of the head of the suspension rods are different from what we ordered. -> Asking company to make the correct ones.

    • Hooking screws cannot go smoothly even they are SDC coated. -> Asking to make the new ones loosely.

    • Cu plates for eddy current damping are oxidized so much. They do not look clean. just covered by bubble packs.
  • Assembled the whole stages
    • Not suspended yet.
    • Found the holes for suspension rods are too small. The company made a mistake on the drawing update.
      • Two plates at Kamioka will be sent to the company. The other plate was re-machined at Mitaka.
    • Cabling around BF takes a lot of time...
  • BF LVDT temporally circuits were made by Miyo-kun, Someya-san, and Hashimoto-san.
  • Second test assembly of BFRM at Mitaka
    • ATC re-machined the holes for suspension rods. -> Will be sent to Kamioka.

    • BFRM was properly suspended.

Plan for coming weeks

  • Suspend BF & BFRM

    • Adjust weight of the BF
    • place the ballast masses and balance it
    • Set LVDT coils on BFRM and check signals
  • Traverser parts will be replaced by Uraguchi-san

Long term to do

  • Calibration of BF LVDT
  • Check acceleration during the installation using the chain-block and jacks

IMMT (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Items that have been delivered.
    • PCB + Metal mask( for Main board(WSD) )
    • Cream solder
  • Redesign(Front panel board for Main 4ch WDS Box and front panel for Ex-I/O Box)Adjust the spacing of the front panel conectors.

Plan for coming weeks

  • I'm planning to perform surface mounting for Power board(WDS Main 4ch Box) in reflow furnace in Akihabara.Since a large PCB size( 320mm * 100mm) is required,a large reflow furnace is necessary,so it can be borrowed in Akihabara(DMM-make site.And of course,paid).
    • ref Peripheral board(Power)PDF

    • ref Reflow furnaceJapanese

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

  • Mirror disassembly jigs (Hirata)

Travel Plans

  • Travel (Week of 2/20):
    • Takahashi: 20- 24
    • Shoda: 21 - 24
    • Mark: 20 - 24
    • Fabian: 20 - 24
    • Okutomi: 20 - 22
    • Fujii:
    • Ishizaki: 20 - 24
    • Hirata: 20 - 24
    • Sato: 20 - 24
    • Enzo: 20 - 24
    • Hashimoto (Hosei Univ.): 20 - 24
    • Ohishi:
    • Tanaka:
  • Travel (Week of 2/27):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Hashimoto (Hosei Univ.):
    • Someya (Hosei Univ.):
    • Ohishi:
    • Tanaka:

Next meeting

On 2017/2/24(Fri) in Mitaka

March VIS F2F: March 3