Agenda/Minutes of the VIS Meeting on 2017/2/17

2017/2/17 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

IMMT (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

Plan for coming weeks

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

  • Mirror disassembly jigs (Hirata)

Travel Plans

  • Travel (Week of 2/20):
    • Takahashi: 20- 24
    • Shoda: 21 - 24
    • Mark: 20 - 24
    • Fabian: 20 - 24
    • Okutomi: 20 - 22
    • Fujii:
    • Ishizaki: 20 - 24
    • Hirata: 20 - 24
    • Sato: 20 - 24
    • Enzo: 20 - 24
    • Hashimoto (Hosei Univ.): 20 - 24
    • Ohishi:
    • Tanaka:
  • Travel (Week of 2/27):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Hashimoto (Hosei Univ.):
    • Someya (Hosei Univ.):
    • Ohishi:
    • Tanaka:

Next meeting

On 2017/2/24(Fri) in Mitaka

March VIS F2F: March 3