*Items that have been delivered. *PCB + Metal mask( for Main board(WSD) ) *Cream solder *Redesign(Front panel board for Main 4ch WDS Box and front panel for Ex-I/O Box) Adjust the spacing of the front panel conectors. *Project-WDS Peripheral circuit PCB Design Ver2(Summary)[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0062/E1706266/001/Project%20WDS%20Peripheral%20circuit%20PCB%20Design%20Ver2-Summry170216.pdf|PDF JGW-E1706266]] *Project-WDS Peripheral circuit PCB Design Version 2(Detail)[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0062/E1706265/001/Project%20WDS%20Peripheral%20circuit%20PCB%20Design%20Ver2%28Detail%29170217.pdf|PDF JGW-E1706265]] *Project-WDS Ex-I/O PCB Design Ver 1(Summary)[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0062/E1706268/002/Project%20WDS%20Ex-IO%20PCB%20Design%20Ver1_1%28Summary%29170217.pdf|PDF JGW-E1706268]] *Project-WDS Ex-I/O PCB Design Ver 1(Detail)[[http://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0062/E1706267/001/Project%20WDS%20Ex-IO%20PCB%20Design%20Ver1%28Detail%29170217.pdf|PDF JGW-E1706267]] |
Agenda/Minutes of the VIS Meeting on 2017/2/17
2017/2/17 13:30 -
Participants:
Progress report
Type-A (Takahashi)
Past week report
Plan for coming weeks
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
IMMT (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
- Items that have been delivered.
- PCB + Metal mask( for Main board(WSD) )
- Cream solder
- Redesign(Front panel board for Main 4ch WDS Box and front panel for Ex-I/O Box)
Adjust the spacing of the front panel conectors.
Project-WDS Peripheral circuit PCB Design Ver2(Summary)PDF JGW-E1706266
Project-WDS Peripheral circuit PCB Design Version 2(Detail)PDF JGW-E1706265
Project-WDS Ex-I/O PCB Design Ver 1(Summary)PDF JGW-E1706268
Project-WDS Ex-I/O PCB Design Ver 1(Detail)PDF JGW-E1706267
Plan for coming weeks
- I'm planning to perform surface mounting for Power board(WDS Main 4ch Box) in reflow furnace in Akihabara.Since a large PCB size( 320mm * 100mm) is required,a large reflow furnace is necessary,so it can be borrowed in Akihabara(DMM-make site.And of course,paid).
ref Peripheral board(Power)PDF
ref Reflow furnaceJapanese
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
- Mirror disassembly jigs (Hirata)
Travel Plans
- Travel (Week of 2/20):
- Takahashi: 20- 24
- Shoda: 21 - 24
- Mark: 20 - 24
- Fabian: 20 - 24
- Okutomi: 20 - 22
- Fujii:
- Ishizaki: 20 - 24
- Hirata: 20 - 24
- Sato: 20 - 24
- Enzo: 20 - 24
- Hashimoto (Hosei Univ.): 20 - 24
- Ohishi:
- Tanaka:
- Travel (Week of 2/27):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Hashimoto (Hosei Univ.):
- Someya (Hosei Univ.):
- Ohishi:
- Tanaka:
Next meeting
On 2017/2/24(Fri) in Mitaka
March VIS F2F: March 3