Agenda/Minutes of the VIS Meeting on 2017/3/24

2017/3/24 13:30 - 14:45

Participants: Mark, Enzo, Perry, Ohishi, Fabian, Hirata, Aso, Tanaka, Shoda, Raffaele, Takahashi, Sato, Ishizaki, Okutomi

Progress report

Schedule Chart : (PDF,MPP)

* Type-A: 2 weeks delay (delay by F2F is taken into account). Try to recover with F2 installation and skipping some part of the PI tuning. * Type-B: Steady progress but 4 weeks delay (out of which, 1 week delay is due to the F2F meeting). Shorten the 3 week long full-TF measurement. * Type-Bp: On schedule (F2F is taken into account).

Type-A (Takahashi)

Past week report

Installation in Y-end:

13th(Mon)

14th(Tue)

15th(Wed)

16th(Thu)

17th(Fri)

21st(Tue)

22nd(Wed)

23rd(Thu)

24th(Fri)

Plan for coming weeks

Type B (Mark)

Report for week of 3/13

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

Report for week of 3/21

At Kamioka (Mark, Fabian, Enzo, Perry, Hirata-san):

Plan for coming weeks

For more detail, see KAGRA/Subgroups/VIS/TypeB/ToDo.

Week of 3/27:

Week of 4/2:

Type-Bp (Shoda)

Past week report

Plan for coming weeks

IMMT (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

Plan for coming weeks

Safety

Discussion

Travel Plans

Next meeting

On 2017/3/31(Fri) VIS F2F: April 7