Line 12: | Line 12: |
Installation in Y-end: 3th(Mon) * Lifted down the maraging wire for cryo-payload into the cryo-shield. 4th(Tue) * Reinstalled the maraging wire for cryo-payload. * Assembled the EQ stop for F2. * Assembled the cables for F2. 5th(Wed) * Assembled the cables for F2-F3. * Put the F2 base onto the end plate of EQ stop with the maraging wire for F3. * Released the keystone of F2. 6th(Thu) * Tuned the F2. The two ballast weights were taken from inside the F2. * Adjust the height of release sensor for F2. * Calibrated the LVDT on F2. |
|
Line 13: | Line 30: |
* Finish the cabling between F2 and F3. * Lift down the F3 stage into the corrugate tube. 10th(Mon): Shipping of the items for X-end by Ishizaki (Mitaka). 11th(Tue): Delivery of the items (Kamioka). Preparation of the transportation to X-end. 12th(Wed): Transportation to X-end by MESCO with Ishizaki. 13th(Thr): Preparation of the replacement of hoist. 14th(Fri): Replacement of the hoist. |
|
Line 39: | Line 64: |
* VIS budget * Budget sheet: https://1drv.ms/x/s!Ajrs5Q_CgYCOhDmdIfYLxfXEMLxs * Budget sheet from SEO: https://1drv.ms/x/s!Ajrs5Q_CgYCOhEJ9sWy16ITB4eII * RMS speed requirements from MIF * http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/subgroup/ifo/MIF/Minutes20170327 |
|
Line 43: | Line 73: |
* Takahashi: * Shoda: * Mark: * Fabian: * Okutomi: |
* Takahashi: 10-14 * Shoda:10-14 * Mark: 10-14 * Fabian: 10-14 * Okutomi: 10-14 |
Line 49: | Line 79: |
* Ishizaki: * Hirata: * Sato: * Enzo: * Hashimoto (Hosei Univ.): |
* Ishizaki: 11-14 * Hirata: 11-14 * Sato: 10-14 * Enzo: 10-14 |
Line 56: | Line 85: |
* Perry: |
* Perry: 10-14 * Sekiguchi(Hosei):11-14 * Hirayama(Hosei):11-14 |
Agenda/Minutes of the VIS Meeting on 2017/4/7
2017/4/7 13:30 -
Participants:
Progress report
Type-A (Takahashi)
Past week report
Installation in Y-end:
3th(Mon)
- Lifted down the maraging wire for cryo-payload into the cryo-shield.
4th(Tue)
- Reinstalled the maraging wire for cryo-payload.
- Assembled the EQ stop for F2.
- Assembled the cables for F2.
5th(Wed)
- Assembled the cables for F2-F3.
- Put the F2 base onto the end plate of EQ stop with the maraging wire for F3.
- Released the keystone of F2.
6th(Thu)
- Tuned the F2. The two ballast weights were taken from inside the F2.
- Adjust the height of release sensor for F2.
- Calibrated the LVDT on F2.
Plan for coming weeks
- Finish the cabling between F2 and F3.
- Lift down the F3 stage into the corrugate tube.
10th(Mon): Shipping of the items for X-end by Ishizaki (Mitaka). 11th(Tue): Delivery of the items (Kamioka). Preparation of the transportation to X-end. 12th(Wed): Transportation to X-end by MESCO with Ishizaki. 13th(Thr): Preparation of the replacement of hoist. 14th(Fri): Replacement of the hoist.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
IMMT (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
- VIS budget
Budget sheet: https://1drv.ms/x/s!Ajrs5Q_CgYCOhDmdIfYLxfXEMLxs
Budget sheet from SEO: https://1drv.ms/x/s!Ajrs5Q_CgYCOhEJ9sWy16ITB4eII
- RMS speed requirements from MIF
Travel Plans
- Travel (Week of 4/10):
- Takahashi: 10-14
Shoda:10-14
- Mark: 10-14
- Fabian: 10-14
- Okutomi: 10-14
- Fujii:
- Ishizaki: 11-14
- Hirata: 11-14
- Sato: 10-14
- Enzo: 10-14
- Ohishi:
- Tanaka:
- Perry: 10-14
- Sekiguchi(Hosei):11-14
- Hirayama(Hosei):11-14
- Travel (Week of 4/17):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Hashimoto (Hosei Univ.):
- Ohishi:
- Tanaka:
Next meeting
On 2017/4/14(Fri)