Agenda/Minutes of the VIS Meeting on 2017/4/21
2017/4/21 13:30 -
Participants:
Progress report
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
Installation in Y-end:
17th(Mon)
- Cleaned the booth and opened the chamber.
- Unpacked the F1 and moved it into the clean booth.
18th(Tue)
- Assembled the end plate 1.
- Checked behavior of F2. The frequency depends on the stress due to the cap.
19th(Wed)
- Extended the EQ stop to the F1 stage.
- Prepared for the F1 damper.
- Cabling of the F1.
- Put the F1 on the EQ stop.
20th(Thu)
- Replaced two release sensors.
- Cabling between F1 and F2.
Plan for coming weeks
- Setting the F1.
- Prepare for the pre-isolator.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
IMMT (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Safety
- Incidents:
- How to protect our heads in the clean booth ?
clean room helmet https://www.monotaro.com/g/00250428/
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Travel Plans
- Travel (Week of 4/24):
- Takahashi: 24-28
- Shoda: 24-28
- Mark: 24-27
- Fabian: 24-26
- Okutomi: 24-28
- Fujii:
- Ishizaki: 24-28
- Hirata: 24-27
- Sato: 24-28
- Enzo: 24-27
- Ohishi:
- Tanaka:
- Perry: 24-28
- Sekiguchi(Hosei): 24-28
- Hirayama(Hosei): 24-28
- Travel (Week of 5/8):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Ohishi:
- Tanaka:
- Perry:
- Sekiguchi(Hosei):
- Hirayama(Hosei):
Next meeting
On 2017/4/28(Fri)