 * Preparation for PR2 installation[
  * Traverser was aligned on the top plate, and moved out of the clean booth.
  * RM was assembled except for the front ring.
  * Assembly frame was set.
   * Hanging frame was not properly set on the assembly frame. we rotated the hanging frame by 180 degrees, and re-set some parts properly.
  * BF LVDTs were assembled and calibrated

 * PRM IM assembly
  * PEEK parts (F00003: support upper mass) are missing though we found them on 1/11/2017...
  * The picomotors at IOO cannot be used for IM because the length is different.
  * The IM was partially assembled and put in the plastic box with un-assembled parts and screws.

 * PR2 gluing
  * All the PR2 flags were removed last weekend.
  * Gluing is on going at Kashiwa.
Line 25: Line 41:
 * Hang the mirror and RM.

Agenda/Minutes of the VIS Meeting on 2017/6/9

2017/6/9 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

  • Preparation for PR2 installation[
    • Traverser was aligned on the top plate, and moved out of the clean booth.
    • RM was assembled except for the front ring.
    • Assembly frame was set.
      • Hanging frame was not properly set on the assembly frame. we rotated the hanging frame by 180 degrees, and re-set some parts properly.
    • BF LVDTs were assembled and calibrated
  • PRM IM assembly
    • PEEK parts (F00003: support upper mass) are missing though we found them on 1/11/2017...
    • The picomotors at IOO cannot be used for IM because the length is different.
    • The IM was partially assembled and put in the plastic box with un-assembled parts and screws.
  • PR2 gluing
    • All the PR2 flags were removed last weekend.
    • Gluing is on going at Kashiwa.

Plan for coming weeks

  • Hang the mirror and RM.

IMMT (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

Plan for coming weeks

Other site works

  • Preparation for the power outage by 6/16
  • Preparation for the PR floor re-work by 6/16

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Travel Plans

* Travel (Week of 6/12):

  • Takahashi: 12-16
  • Shoda: 12-16
  • Mark: 12-16
  • Fabian: 12-16
  • Okutomi: 12-16
  • Fujii:
  • Ishizaki: CAD work in Mitaka
  • Hirata: 12-16
  • Sato: 12-16
  • Enzo: 12-16
  • Ohishi:
  • Tanaka:
  • Akiyama(Hosei): 13-16
  • Hashimoto(Hosei): 12-15
  • Travel (Week of 6/19):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:
    • Tanaka:
    • Akiyama(Hosei):
    • Hashimoto(Hosei):

Next meeting

On 2017/6/16(Fri) Next F2F: 6/30(Fri)