Agenda/Minutes of the VIS Meeting on 2017/6/16
2017/6/16 13:30 -
Participants:
Progress report
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
Plan for coming weeks
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
IMMT (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Other site works
- Preparation for the power outage by 6/16
- Preparation for the PR floor re-work by 6/16
- 6/19: Power outage
- 6/21: Safety lecture after the morning briefing
- 6/21 11:30 - 12:30: Crane inspection
6/20 -24: BS & PR booth: lighting installation (BS and PR2 area 6/23 afternoon)
- 6/22-23: PR area: floor fix
- 6/26-30: PR area: stainless steel flooring
- 6/28: Maintenance of the rapid charger for the electric vehicles
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Travel Plans
- Travel (Week of 6/19):
- Takahashi: 20-23
- Shoda: 20-23
- Mark: 19-23
- Fabian: 20-22
- Okutomi: 20-23
- Fujii:
- Ishizaki: 20-23
- Hirata: 20-23
- Sato: 20-23
- Enzo: 20-22
- Ohishi:
- Tanaka:
- Akiyama(Hosei): 20-23
- Hashimoto(Hosei): 20-22
- Travel (Week of 6/26):
- Takahashi:
- Shoda:
- Mark:
- Fabian:
- Okutomi:
- Fujii:
- Ishizaki:
- Hirata:
- Sato:
- Enzo:
- Ohishi:
- Tanaka:
- Akiyama(Hosei):
- Hashimoto(Hosei):
Next meeting
On 2017/6/23(Fri) Next F2F: 6/30(Fri)