Agenda/Minutes of the VIS Meeting on 2017/6/16
2017/6/16 13:30 - 15:00
Participants: Takahashi, Sato, Aso, Fujii, Okutomi, Ohishi, Tanaka, Akutsu, Shoda, Enzo, Fabian, Hirata, Mark, Raffaele, Ishizaki
Progress report
- Type-A: 0.5 week delay
- Type-B: 8 weeks delay
- Type-Bp: 1 week delay
Type-A (Takahashi)
Past week report
Installation in Y-end:
12th(Mon)
- Adjusted the tilt of BF by moving masses.
- Checked geometry around the BF.
13th(Tue)
- Adjusted the height of damper ring for the BF.
- Adjusted the yaw rotation of BF.
- Attached the LVDT coils and checked the movable range.
- Attached the cable clamps onto the TF.
- Removed the wire clamp.
14th(Wed)
- Tuned the TF to frequency less than 0.2Hz changing the compression of blades.
- Assembled the cables for BF damper.
- Cabled from the F1 to the TF.
15th(Thu)
- Made flip cables.
- Cabled around the BF damper.
- Tuned the LVDT driver.
- Checked the assembly of geophone pods.
16th(Fri)
- Prepared for the power outage.
Plan for coming weeks
- Check of the BF damper.
- Cabling to the feedthroughs.
- Setting of the ACCs.
- Preparation in X-end.
Type B (Mark)
Past week report
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
- Hirata-san and Sekine-san moved the tank lid and service port ring to the pallet with the crane and covered the open tank with the spare clean bag.
- Hirata-san and Mark got the LBB damper rings assembled and installed. A joint part for the Cu ring needed to have holes enlarged because the hole pattern did not quite match that on the half-ring. The magnet ring is hanging in the chamber and the Cu ring is attached below it with clamps, ready to receive the rods that will hang down from the PI.
- Hirata-san recounted all the unused cables.
- Hirata-san installed the outrigger parts on the LBB, which will receive the rods coming down from the damper ring.
- Enzo and Mark tested all the stepper motors.
- Enzo and Mark debugged the PI horizontal LVDTs. One LVDT had a flaky connection and one card in the LVDT driver had three dead channels. Enzo created a fully working driver using parts from another driver that also had a faulty card.
- Fabian adjusted the ballast mass on the SF to get good pitch/roll/vertical adjustment and attached it with screws.
- Fabian set up the optical lever again (the PR2 team had repossessed the breadboard we had been using but Akutsu-san supplied another one).
- Enzo and Mark tested the pico motors. The software is very unreliable, but we we able to confirm that the IM pitch pico works.
- The whole team wrapped items and shut down equipment ahead of the power outage.
Plan for coming weeks
- Recover from power outage.
- Crane suspension into tank.
Type-Bp (Shoda)
Past week report
- Mirror preparation
- We glued the wire breakers and flags on the PR2 mirror on last Friday, but they detached when I checked on Sunday.
- Therefore, we tried the gluing again on Monday, and checked Tuesday evening. But they did not fixed again.
- We tried again on Thursday, and it is curing time now. This time, we have put more glue on them.
- Other preparation
- We assembled PR2 BF LVDTs and PRM BF LVDTs. They are all calibrated.
- We almost finished cabling between the field rack and clean room for PR2.
- PRM circuits are also almost ready. Not cabled yet.
- PR3 measurement
- Fujii-kun measured the properties of PR3.
- We found the one of the coil driver is not working well. The current for PR3/PRM rack and IOO rack was not enough. The problem of the current was fixed with Nakano-kun, but the driver might have been driven with saturated status, which might cause the problem. Actually, the problem was fixed later somehow. We do not know why yet...
Miyakawa-san is asking us to report the circuits problem via e-mails when they occur in order to record them.
Plan for coming weeks
- Mirror/RM hanging (if they are properly fixed...)
IMMT (Ohishi)
Past week report
- Removed IMMT2 mirror from IFI chamber
- Hirose-san will carry both IMMT1 and IMMT2 mirrors to Kashiwa.
Plan for coming weeks
- Hirose-san will put first contact on HR surface of mirrors.
- FCL prepare jig parts.
Watchdog system (Tanaka)
Past week report
- Examination of experimental preamplifier circuit fabrication.
- I'm checking the operation of the fabricated circuit.
- Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).
- Request a quote for electronic parts etc(Estimating at Univ.Tokyo.co-op).
- Other estimates are complete(PCB etc).
Plan for coming weeks
Examination of experimental preamplifier circuit fabrication. -->Ongoing.
Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.
Other site works
- Preparation for the power outage by 6/16
- Preparation for the PR floor re-work by 6/16
- 6/19: Power outage
- 6/21: Safety lecture after the morning briefing
- 6/21 11:30 - 12:30: Crane inspection
6/20 -24: BS & PR booth: lighting installation (BS and PR2 area 6/23 afternoon)
- 6/22-23: PR area: floor fix
- 6/26-30: PR area: stainless steel flooring
- 6/28: Maintenance of the rapid charger for the electric vehicles
Safety
- Incidents: no
- Foreseen risks
- Type-A: Open the chamber. Crane works in both ends.
- Type-B: Heavy crane work.
- Type-Bp: Mirror hanging.
Discussion
Type-A
- Tasks for 6/19 (Mon) (Takahashi)
- Make a detailed schedule for X-End
- Make a list of missing items for X-End and put it on the VIS Type-A wiki
Type-B
- Tentative schedule after the installation into the chamber
- 6/20 installation into the chamber
- 6/21-22 Cabling, balancing
- 6/23 prepare for the TF measurements (using OSEMs)
- Measure TFs during the weekend
6/26 OpLev installation (Simon)
- Somewhere in the week of 6/26: gluing of the real BS
- In the week of July 3: remove the suspension from the chamber
- Make a list of tasks for the preparation of the real BS installation (Mark, to be done on 6/19).
- Assign people to the above tasks (Mark)
Travel Plans
- Travel (Week of 6/19):
- Takahashi: 20-23
- Shoda: 20-23
- Mark: 19-23
- Fabian: 20-22
- Okutomi: 20-23
- Fujii: 20 - 22
- Ishizaki: 20-23
- Hirata: 20-23
- Sato: 20-23
- Enzo: 20-22
- Ohishi:
- Tanaka:
- Akiyama(Hosei): 20-23
- Hashimoto(Hosei): 20-22
- Travel (Week of 6/26):
- Takahashi: 26 - 29
- Shoda: 26 - 29
- Mark: 26 - 29 (?)
- Fabian: 26 - 29 (?)
- Okutomi: 26 - 29
- Fujii:
- Ishizaki: 26 - 29
- Hirata: 26 - 29 (?)
- Sato: 26 - 29
- Enzo: 27 - 29 (?)
- Ohishi:
- Tanaka:
- Akiyama(Hosei): 27 - 29
- Hashimoto(Hosei): 26 - 29
Next meeting
On 2017/6/23(Fri) Next F2F: 6/30(Fri)