Differences between revisions 10 and 11
Revision 10 as of 2017-06-23 11:42:13
Size: 2713
Editor: YoichiAso
Comment:
Revision 11 as of 2017-06-23 12:13:18
Size: 3468
Comment:
Deletions are marked like this. Additions are marked like this.
Line 58: Line 58:
Line 60: Line 61:
 *Examination of experimental preamplifier circuit fabrication. -->
   *I completed the performance test of the PreAmp. for use on the KAGRA side.However,data analysis is in progress.Report(JGW-E1706850)[[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0068/E1706850/001/Project%20WDS%20PreAmp%20Design%20170623.pdf|PDF]]
 *Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
   *Estimate --> completed.
   *Waiting for purchase of goods.
Line 61: Line 68:
 *Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.

 *Examination of experimental preamplifier circuit fabrication. -->Ongoing.

 *Adjustment of experiment schedule etc. in the KAGRA side start.

Agenda/Minutes of the VIS Meeting on 2017/6/23

2017/6/23 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

Installation in Y-end/X-end:

20th(Tue)

  • Recovered from the power outage.
  • Opend the chamber.
  • Tuned the TF by changing the compression of blades again.
  • Disassembled the bridge frame.

21th(Wed)

  • Continued the tuning of TF to 0.2Hz.
  • Released the IP and adjusted the tilt of the IP base.
  • Checked the FR for TF. The FR was not working.
  • Made the cables for ACC.
  • Transported some items from the Y-end to the X-end.

22th(Thu)

Y-end

  • Tuned the IP roughly. The frequency is 80mHz.
  • Adujusted the centering of IP by the tilt of IP base and the motor sliders.
  • Started cabling from the TF to the feedthroughs.

X-end

  • Cleaned the floor.
  • Covered the floor by SUS sheets.

Plan for coming weeks

  • Setting of the BF damper.
  • Cabling to the feedthroughs.
  • Setting of the ACCs.
  • Preparatioin in X-end.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

IMMT (Ohishi)

Past week report

  • Drawing some parts related with IMMT; coil holder support, etc.

Plan for coming weeks

  • 6/27(Tue)-28(Wed) Magnets and standoffs gluing at Kashiwa

Watchdog system (Tanaka)

Past week report

  • Examination of experimental preamplifier circuit fabrication. -->

    • I completed the performance test of the PreAmp. for use on the KAGRA side.However,data analysis is in progress.Report(JGW-E1706850)PDF

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->

    • Estimate --> completed.

    • Waiting for purchase of goods.

Plan for coming weeks

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.

  • Examination of experimental preamplifier circuit fabrication. -->Ongoing.

  • Adjustment of experiment schedule etc. in the KAGRA side start.

Other site works

  • 6/26-30: PR area: stainless steel flooring
  • 6/28: Maintenance of the rapid charger for the electric vehicles

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

  • Cable purchase

Travel Plans

* Travel (Week of 6/26):

  • Takahashi: 26 - 29
  • Shoda: 26 - 29
  • Mark: 26 - 29 (?)
  • Fabian: 26 - 29 (?)
  • Okutomi: 26 - 29
  • Fujii:
  • Ishizaki: 26 - 29
  • Hirata: 26 - 29 (?)
  • Sato: 26 - 29
  • Enzo: 27 - 29 (?)
  • Ohishi:
  • Tanaka:
  • Akiyama(Hosei): 27 - 29
  • Hashimoto(Hosei): 26 - 29
  • Travel (Week of 7/3):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:
    • Tanaka:
    • Akiyama(Hosei):
    • Hashimoto(Hosei):

Next meeting

On 2017/6/30(Fri) Next F2F: 7/??