Agenda/Minutes of the VIS Meeting on 2017/6/23
2017/6/23 13:30 - 15:00
Participants: Mark, Okutomi, Sato, Ohishi, Aso, Ishizaki, Fabian, Enzo, Shoda, Raffaele, Akutsu, Tanaka, Takahashi
Progress report
- Type-A: A week delay in Y-End. On schedule for X-End but the X-End schedule need to be shortened.
- Type-B: Updating the real BS installation schedule.
- Type-Bp: 2 weeks delay by the gluing problem, but progressed other works scheduled later.
Type-A (Takahashi)
Past week report
Installation in Y-end/X-end:
20th(Tue)
- Recovered from the power outage.
- Opend the chamber.
- Tuned the TF by changing the compression of blades again.
- Disassembled the bridge frame.
21th(Wed)
- Continued the tuning of TF to 0.2Hz.
- Released the IP and adjusted the tilt of the IP base.
- Checked the FR for TF. The FR was not working.
- Made the cables for ACC.
- Transported some items from the Y-end to the X-end.
22th(Thu)
Y-end
- Tuned the IP roughly. The frequency is 80mHz.
- Adujusted the centering of IP by the tilt of IP base and the motor sliders.
- Started cabling from the TF to the feedthroughs.
X-end
- Cleaned the floor.
- Covered the floor by SUS sheets.
Plan for coming weeks
- Setting of the BF damper.
- Cabling to the feedthroughs.
- Setting of the ACCs.
- Preparatioin in X-end.
Type B (Mark)
Past week report
At Kamioka (Mark, Fabian, Enzo, Hirata-san):
- We disconnected the in-vacuum and in-air cabling from the feedthroughs.
- We removed crossbars below BF and SF.
- We set the SF damper to 4 mm clearance.
- We adjusted the jacks to nominal height.
- We removed the geophones and PI yaw stepper for craning.
- We craned the suspension into the tank, and hooked the LBB Cu ring.
- We replaced the geophones etc.
- We unlocked all but the IP and adjusted the jacks until the pendulum was centered in the security structure.
- We unlocked the IP and adjusted to to center with the jacks and fishing rods.
- We craned the vacuum tank lid+ring back on, and then removed just the lid (only).
- We unclamped the LBB damper rings and removed the spacers.
- We removed the blocks and shims supporting the LBB, inserted the long screw feet and hooked the LBB to the Cu damper ring.
- We added 2*31.5 kg of ballast to the LBB, which got the blades to the point where firm pressure would depress the tips.
- We reconnected the in-vacuum cabling. In ≈15 places we opted to omit the Type 1 cable and use a F-F gender bender.
- We reconnected all but four of the in-air cables.
Plan for week of 6/26
Mark and Enzo at Kamioka:
- Double-check where gender-benders were used.
- Finish connecting in-air cabling.
- Debug all cabling.
- Work with Simon to set up LSOL.
Fabian at Mitaka:
- Design final ballast masses for IM, BF and SF assuming no BF rebuild (needs to be adaptable).
- Check all items for BS flag/prism gluing are available (prisms, flags, jigs, mirror box, glue, scale, mixing tools etc).
Hirata-san at Mitaka:
- Do new 3D CAD:
- BS Test Hang build, with top of tank, full suspension, and LBB damper all reversed.
- Final BS build, as above, but with everything BF down rotated back to original.
- In-tank version.
- On-assembly-frame version. (Adjust jack positions if possible, or leave for Mark to do.)
- SR2 on BS assembly frame. (Adjust jack positions if possible, or leave for Mark to do.)
Type-Bp (Shoda)
Past week report
- The wire breaker still refused to be attached.
- We tried two more times (on Tuesday and Wednesday). The 2nd wire breaker was attached. But the 1st wire breaker still have not been glued.
- We tried gluing again today at IYC clean booth.
- The temperature change by 3 degrees during the power outage, which corresponds to about 2 mm height change per 1 GAS filter. And the temperature seems to change more if the power is not turned on for longer time.
- PRM optical bench intermediate ring and damper ring are prepared and set inside the PRM chamber.
- PRM cabling is almost ready at outside the clean booth.
- BIO system is implemented into the PR3 model, but we need help of Kokeyama-san or Miyakawa-san in order to increase the BIO card more than 10.
Plan for coming weeks
- Please glued. Then mirror hanging.
IMMT (Ohishi)
Past week report
- Drawing some parts related with IMMT; coil holder support, etc.
Plan for coming weeks
- 6/27(Tue)-28(Wed) Magnets and standoffs gluing at Kashiwa
Watchdog system (Tanaka)
Past week report
Examination of experimental preamplifier circuit fabrication. -->
Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
Estimate --> completed.
- Waiting for purchase of goods.
Plan for coming weeks
Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.
Examination of experimental preamplifier circuit fabrication. -->Ongoing.
- Adjustment of experiment schedule etc. in the KAGRA side start.
Other site works
- 6/26-30: PR area: stainless steel flooring
- 6/28: Maintenance of the rapid charger for the electric vehicles
Safety
- Incidents: no
- Foreseen risks
- Type-A: Crane work to close the chamber
- Type-B: Close the lid back on
- Type-Bp: Mirror hanging
Discussion
Type-A
- The immovable FR on the TF will be fixed after the CRY test hanging is finished.
- X-End schedule is too tight. We need to find ways to expedite the schedule. Takahashi and Aso will discuss it in the next week.
Type-B
- We want to do the gluing work of the real BS in the week of July 3rd.
- We need a Pelican box for the transportation of BS.
- Will check the size of the existing Pelican box to see if the BS mirror box fits in.
- Mark will talk to Hirose-san about the gluing schedule and the Pelican box issue.
Type-Bp
- The schedule is delayed by the gluing problem.
- Aso will check the impact of this to the commissioning schedule
Cable purchase
- Type-B wants to use much shorter cables to connect from the suspension to the flange.
- Will talk to Sato-san after the meeting.
Travel Plans
- Travel (Week of 6/26):
- Takahashi: 26 - 29
- Shoda: 26 - 29
- Mark: 26 - 29
- Fabian:
- Okutomi: 26 - 29
- Fujii:
- Ishizaki: 26 - 29
- Hirata:
- Sato: 26 - 29
- Enzo: 27 - 29
- Simon: 26 - ??
- Ohishi: 27 - 28 (Kashiwa)
- Tanaka:
- Akiyama(Hosei): 27 - 29
- Hashimoto(Hosei): 26 - 29
- Travel (Week of 7/3):
- Takahashi: 3 - 7
- Shoda: 3 - 7
- Mark: TBD
- Fabian: TBD
- Okutomi: 3 - 7
- Fujii:
- Ishizaki: 3 - 7
- Hirata: TBD
- Sato: 3 - 7
- Enzo: TBD
- Ohishi:
- Tanaka:
- Komori (Ando lab.): 3 - 7
- Hashimoto(Hosei): 3 - 6
Next meeting
On 2017/6/30(Fri) Next F2F: 7/??