Differences between revisions 14 and 15
Revision 14 as of 2017-06-23 15:17:14
Size: 4421
Editor: YoichiAso
Comment:
Revision 15 as of 2017-06-23 15:24:53
Size: 5481
Editor: YoichiAso
Comment:
Deletions are marked like this. Additions are marked like this.
Line 12: Line 12:
 * Type-Bp:  * Type-Bp: 2 weeks delay by the gluing problem, but progressed other works scheduled later.
Line 92: Line 92:
 * Incidents:  * Incidents: no
Line 95: Line 95:
  * Type-A:
  * Type-B:
  * Type-Bp:
  * Type-A: Crane work to close the chamber
  * Type-B: Close the lid back on
  * Type-Bp: Mirror hanging
Line 101: Line 102:
 * Cable purchase === Type-A ===
 * The immovable FR on the TF will be fixed after the CRY test hanging is finished.
 * X-End schedule is too tight. We need to find ways to expedite the schedule. Takahashi and Aso will discuss it in the next week.

=== Type-B ===
 * We want to do the gluing work of the real BS in the week of July 3rd.
 * We need a Pelican box for the transportation of BS.
  * Will check the size of the existing Pelican box to see if the BS mirror box fits in.
 * Mark will talk to Hirose-san about the gluing schedule and the Pelican box issue.

=== Type-Bp ===
 * The schedule is delayed by the gluing problem.
  * Aso will check the impact of this to the commissioning schedule

=== Cable purchase ===
 * Type-B wants to use much shorter cables to connect from the suspension to the flange.
  * Will talk to Sato-san after the meeting.
Line 107: Line 124:
  * Mark: 26 - 29 (?)
  * Fabian: 26 - 29 (?)
  * Mark: 26 - 29
  * Fabian:
Line 112: Line 129:
  * Hirata: 26 - 29 (?)   * Hirata:
Line 114: Line 131:
  * Enzo: 27 - 29 (?)
  * Ohishi:
  * Enzo: 27 - 29
  * Simon: 26 -
??
  * Ohishi: 27 - 28 (Kashiwa)
Line 121: Line 139:
  * Takahashi:
  * Shoda:
  * Mark:
  * Fabian:
  * Okutomi:
  * Takahashi: 3 - 7
  * Shoda: 3 - 7
  * Mark: TBD
  * Fabian: TBD
  * Okutomi: 3 - 7
Line 127: Line 145:
  * Ishizaki:
  * Hirata:
  * Sato:
  * Enzo:
  * Ishizaki: 3 - 7
  * Hirata: TBD
  * Sato: 3 - 7
  * Enzo: TBD
Line 133: Line 151:
  * Akiyama(Hosei):
  * Hashimoto(Hosei):
  * Komori (Ando lab.): 3 - 7
  * Hashimoto(Hosei): 3 - 6

Agenda/Minutes of the VIS Meeting on 2017/6/23

2017/6/23 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

  • Type-A: A week delay in Y-End. On schedule for X-End but the X-End schedule need to be shortened.
  • Type-B: Updating the real BS installation schedule.
  • Type-Bp: 2 weeks delay by the gluing problem, but progressed other works scheduled later.

Type-A (Takahashi)

Past week report

Installation in Y-end/X-end:

20th(Tue)

  • Recovered from the power outage.
  • Opend the chamber.
  • Tuned the TF by changing the compression of blades again.
  • Disassembled the bridge frame.

21th(Wed)

  • Continued the tuning of TF to 0.2Hz.
  • Released the IP and adjusted the tilt of the IP base.
  • Checked the FR for TF. The FR was not working.
  • Made the cables for ACC.
  • Transported some items from the Y-end to the X-end.

22th(Thu)

Y-end

  • Tuned the IP roughly. The frequency is 80mHz.
  • Adujusted the centering of IP by the tilt of IP base and the motor sliders.
  • Started cabling from the TF to the feedthroughs.

X-end

  • Cleaned the floor.
  • Covered the floor by SUS sheets.

Plan for coming weeks

  • Setting of the BF damper.
  • Cabling to the feedthroughs.
  • Setting of the ACCs.
  • Preparatioin in X-end.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

  • The wire breaker still refused to be attached.
    • We tried two more times (on Tuesday and Wednesday). The 2nd wire breaker was attached. But the 1st wire breaker still have not been glued.
    • We tried gluing again today at IYC clean booth.
  • The temperature change by 3 degrees during the power outage, which corresponds to about 2 mm height change per 1 GAS filter. And the temperature seems to change more if the power is not turned on for longer time.
  • PRM optical bench intermediate ring and damper ring are prepared and set inside the PRM chamber.
  • PRM cabling is almost ready at outside the clean booth.
  • BIO system is implemented into the PR3 model, but we need help of Kokeyama-san or Miyakawa-san in order to increase the BIO card more than 10.

Plan for coming weeks

  • Please glued. Then mirror hanging.

IMMT (Ohishi)

Past week report

  • Drawing some parts related with IMMT; coil holder support, etc.

Plan for coming weeks

  • 6/27(Tue)-28(Wed) Magnets and standoffs gluing at Kashiwa

Watchdog system (Tanaka)

Past week report

  • Examination of experimental preamplifier circuit fabrication. -->

    • I completed the performance test of the PreAmp. for use on the KAGRA side.However,data analysis is in progress.Report(JGW-E1706850)PDF

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->

    • Estimate --> completed.

    • Waiting for purchase of goods.

Plan for coming weeks

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.

  • Examination of experimental preamplifier circuit fabrication. -->Ongoing.

  • Adjustment of experiment schedule etc. in the KAGRA side start.

Other site works

  • 6/26-30: PR area: stainless steel flooring
  • 6/28: Maintenance of the rapid charger for the electric vehicles

Safety

  • Incidents: no
  • Foreseen risks
    • Type-A: Crane work to close the chamber
    • Type-B: Close the lid back on
    • Type-Bp: Mirror hanging

Discussion

Type-A

  • The immovable FR on the TF will be fixed after the CRY test hanging is finished.
  • X-End schedule is too tight. We need to find ways to expedite the schedule. Takahashi and Aso will discuss it in the next week.

Type-B

  • We want to do the gluing work of the real BS in the week of July 3rd.
  • We need a Pelican box for the transportation of BS.
    • Will check the size of the existing Pelican box to see if the BS mirror box fits in.
  • Mark will talk to Hirose-san about the gluing schedule and the Pelican box issue.

Type-Bp

  • The schedule is delayed by the gluing problem.
    • Aso will check the impact of this to the commissioning schedule

Cable purchase

  • Type-B wants to use much shorter cables to connect from the suspension to the flange.
    • Will talk to Sato-san after the meeting.

Travel Plans

  • Travel (Week of 6/26):
    • Takahashi: 26 - 29
    • Shoda: 26 - 29
    • Mark: 26 - 29
    • Fabian:
    • Okutomi: 26 - 29
    • Fujii:
    • Ishizaki: 26 - 29
    • Hirata:
    • Sato: 26 - 29
    • Enzo: 27 - 29
    • Simon: 26 - ??
    • Ohishi: 27 - 28 (Kashiwa)
    • Tanaka:
    • Akiyama(Hosei): 27 - 29
    • Hashimoto(Hosei): 26 - 29
  • Travel (Week of 7/3):
    • Takahashi: 3 - 7
    • Shoda: 3 - 7
    • Mark: TBD
    • Fabian: TBD
    • Okutomi: 3 - 7
    • Fujii:
    • Ishizaki: 3 - 7
    • Hirata: TBD
    • Sato: 3 - 7
    • Enzo: TBD
    • Ohishi:
    • Tanaka:
    • Komori (Ando lab.): 3 - 7
    • Hashimoto(Hosei): 3 - 6

Next meeting

On 2017/6/30(Fri) Next F2F: 7/??

KAGRA/Subgroups/VIS/VISMinutes20170623 (last edited 2017-06-23 20:29:02 by MarkBarton)