Line 12: | Line 12: |
* Type-Bp: | * Type-Bp: 2 weeks delay by the gluing problem, but progressed other works scheduled later. |
Line 92: | Line 92: |
* Incidents: | * Incidents: no |
Line 95: | Line 95: |
* Type-A: * Type-B: * Type-Bp: |
* Type-A: Crane work to close the chamber * Type-B: Close the lid back on * Type-Bp: Mirror hanging |
Line 101: | Line 102: |
* Cable purchase | === Type-A === * The immovable FR on the TF will be fixed after the CRY test hanging is finished. * X-End schedule is too tight. We need to find ways to expedite the schedule. Takahashi and Aso will discuss it in the next week. === Type-B === * We want to do the gluing work of the real BS in the week of July 3rd. * We need a Pelican box for the transportation of BS. * Will check the size of the existing Pelican box to see if the BS mirror box fits in. * Mark will talk to Hirose-san about the gluing schedule and the Pelican box issue. === Type-Bp === * The schedule is delayed by the gluing problem. * Aso will check the impact of this to the commissioning schedule === Cable purchase === * Type-B wants to use much shorter cables to connect from the suspension to the flange. * Will talk to Sato-san after the meeting. |
Line 107: | Line 124: |
* Mark: 26 - 29 (?) * Fabian: 26 - 29 (?) |
* Mark: 26 - 29 * Fabian: |
Line 112: | Line 129: |
* Hirata: 26 - 29 (?) | * Hirata: |
Line 114: | Line 131: |
* Enzo: 27 - 29 (?) * Ohishi: |
* Enzo: 27 - 29 * Simon: 26 - ?? * Ohishi: 27 - 28 (Kashiwa) |
Line 121: | Line 139: |
* Takahashi: * Shoda: * Mark: * Fabian: * Okutomi: |
* Takahashi: 3 - 7 * Shoda: 3 - 7 * Mark: TBD * Fabian: TBD * Okutomi: 3 - 7 |
Line 127: | Line 145: |
* Ishizaki: * Hirata: * Sato: * Enzo: |
* Ishizaki: 3 - 7 * Hirata: TBD * Sato: 3 - 7 * Enzo: TBD |
Line 133: | Line 151: |
* Akiyama(Hosei): * Hashimoto(Hosei): |
* Komori (Ando lab.): 3 - 7 * Hashimoto(Hosei): 3 - 6 |
Agenda/Minutes of the VIS Meeting on 2017/6/23
2017/6/23 13:30 -
Participants:
Progress report
- Type-A: A week delay in Y-End. On schedule for X-End but the X-End schedule need to be shortened.
- Type-B: Updating the real BS installation schedule.
- Type-Bp: 2 weeks delay by the gluing problem, but progressed other works scheduled later.
Type-A (Takahashi)
Past week report
Installation in Y-end/X-end:
20th(Tue)
- Recovered from the power outage.
- Opend the chamber.
- Tuned the TF by changing the compression of blades again.
- Disassembled the bridge frame.
21th(Wed)
- Continued the tuning of TF to 0.2Hz.
- Released the IP and adjusted the tilt of the IP base.
- Checked the FR for TF. The FR was not working.
- Made the cables for ACC.
- Transported some items from the Y-end to the X-end.
22th(Thu)
Y-end
- Tuned the IP roughly. The frequency is 80mHz.
- Adujusted the centering of IP by the tilt of IP base and the motor sliders.
- Started cabling from the TF to the feedthroughs.
X-end
- Cleaned the floor.
- Covered the floor by SUS sheets.
Plan for coming weeks
- Setting of the BF damper.
- Cabling to the feedthroughs.
- Setting of the ACCs.
- Preparatioin in X-end.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
- The wire breaker still refused to be attached.
- We tried two more times (on Tuesday and Wednesday). The 2nd wire breaker was attached. But the 1st wire breaker still have not been glued.
- We tried gluing again today at IYC clean booth.
- The temperature change by 3 degrees during the power outage, which corresponds to about 2 mm height change per 1 GAS filter. And the temperature seems to change more if the power is not turned on for longer time.
- PRM optical bench intermediate ring and damper ring are prepared and set inside the PRM chamber.
- PRM cabling is almost ready at outside the clean booth.
- BIO system is implemented into the PR3 model, but we need help of Kokeyama-san or Miyakawa-san in order to increase the BIO card more than 10.
Plan for coming weeks
- Please glued. Then mirror hanging.
IMMT (Ohishi)
Past week report
- Drawing some parts related with IMMT; coil holder support, etc.
Plan for coming weeks
- 6/27(Tue)-28(Wed) Magnets and standoffs gluing at Kashiwa
Watchdog system (Tanaka)
Past week report
Examination of experimental preamplifier circuit fabrication. -->
Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
Estimate --> completed.
- Waiting for purchase of goods.
Plan for coming weeks
Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing.
Examination of experimental preamplifier circuit fabrication. -->Ongoing.
- Adjustment of experiment schedule etc. in the KAGRA side start.
Other site works
- 6/26-30: PR area: stainless steel flooring
- 6/28: Maintenance of the rapid charger for the electric vehicles
Safety
- Incidents: no
- Foreseen risks
- Type-A: Crane work to close the chamber
- Type-B: Close the lid back on
- Type-Bp: Mirror hanging
Discussion
Type-A
- The immovable FR on the TF will be fixed after the CRY test hanging is finished.
- X-End schedule is too tight. We need to find ways to expedite the schedule. Takahashi and Aso will discuss it in the next week.
Type-B
- We want to do the gluing work of the real BS in the week of July 3rd.
- We need a Pelican box for the transportation of BS.
- Will check the size of the existing Pelican box to see if the BS mirror box fits in.
- Mark will talk to Hirose-san about the gluing schedule and the Pelican box issue.
Type-Bp
- The schedule is delayed by the gluing problem.
- Aso will check the impact of this to the commissioning schedule
Cable purchase
- Type-B wants to use much shorter cables to connect from the suspension to the flange.
- Will talk to Sato-san after the meeting.
Travel Plans
- Travel (Week of 6/26):
- Takahashi: 26 - 29
- Shoda: 26 - 29
- Mark: 26 - 29
- Fabian:
- Okutomi: 26 - 29
- Fujii:
- Ishizaki: 26 - 29
- Hirata:
- Sato: 26 - 29
- Enzo: 27 - 29
- Simon: 26 - ??
- Ohishi: 27 - 28 (Kashiwa)
- Tanaka:
- Akiyama(Hosei): 27 - 29
- Hashimoto(Hosei): 26 - 29
- Travel (Week of 7/3):
- Takahashi: 3 - 7
- Shoda: 3 - 7
- Mark: TBD
- Fabian: TBD
- Okutomi: 3 - 7
- Fujii:
- Ishizaki: 3 - 7
- Hirata: TBD
- Sato: 3 - 7
- Enzo: TBD
- Ohishi:
- Tanaka:
- Komori (Ando lab.): 3 - 7
- Hashimoto(Hosei): 3 - 6
Next meeting
On 2017/6/30(Fri) Next F2F: 7/??