Line 32: Line 32:
   *Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
        *Ongoing -->
             *Order electronic parts -->Done.
             *Order PCB's(Ex-I/O Interface and relative PCB's) -->Ordering(PCB data of vendor is in progress).
Line 33: Line 38:
   *Start production of equipment(As soon as parts are delivered).
   *Adjustment of experiment schedule etc. in the KAGRA side start. --> Ongoing.

Agenda/Minutes of the VIS Meeting on 2017/7/7

2017/7/7 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

IMMT (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->

    • Ongoing -->

      • Order electronic parts -->Done.

      • Order PCB's(Ex-I/O Interface and relative PCB's) -->Ordering(PCB data of vendor is in progress).

Plan for coming weeks

  • Start production of equipment(As soon as parts are delivered).
  • Adjustment of experiment schedule etc. in the KAGRA side start. --> Ongoing.

Other site works

  • 7/10-?: Lighting installation in the MCE and SR clean booths

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Travel Plans

  • Travel (Week of 7/10):
    • Takahashi: 10 - 14
    • Okutomi: 10 - 14
    • Sato: 10 - 14
    • Ishizaki: 10 - 13
    • Mark: 10 - 14
    • Fabian: 10 - 14
    • Hirata: 10 - 14
    • Enzo: 10 - 14
    • Shoda: 10 - 14
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Komori (Ando lab.): 10 - 14
    • Hashimoto(Hosei): 10 - 13
  • Travel (Week of 7/17):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Komori (Ando lab.):
    • Hashimoto(Hosei):

Next meeting

On 2017/7/14(Fri) Next F2F: 7/??

KAGRA/Subgroups/VIS/VISMinutes20170707 (last edited 2017-07-07 15:18:14 by YoichiAso)