Agenda/Minutes of the VIS Meeting on 2017/8/18
2017/8/18 13:30 -
Participants:
Progress report
Schedule Chart
Schedule summary
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
[X-end]
16th(Wed)
- Assembled the end plate for F2.
- Prepared for the F2.
- Extended the EQ stop to the F2 stage.
- Put the F2 onto the end plate. The F3 was suspended from the F2.
- Removed a ballast from the F3.
17th(Thu)
- Checked the ACCs.
18th(Fri)
- Closed the F3 cap.
Plan for coming weeks
- Installation of the Filter2 in X-end.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
IMMT (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Other site works
- 8/23-24 Draft Chamber Installation
- 8/28 11:30 - 12:30 crane inspection
- End of Aug. to Nov.: Mozumi entrance will be closed
Safety
- Incidents:
- EP-30 safety
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
- When to install the middle flange for ETMX
Travel Plans
- Travel (Week of 8/21):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Hashimoto(Hosei):
- Yoshioka (Toyama):
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 8/28):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Hashimoto(Hosei):
- Yoshioka (Toyama):
- Kozu (ICRR):
Next meeting
On 2017/8/25(Fri)