Agenda/Minutes of the VIS Meeting on 2017/9/22

2017/9/22 13:30 -

Participants:


Progress report

Schedule Chart

Type-A & Bp : (PDF,MPP)

Type-B: (PDF,MPP)

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

*Waiting for concrete information on installation location.The type(High power,Low power)and number actually needed,and the peripheral equipment accompanying it.-->Waiting for information provision.

*I held a meeting to make estimates with several vendors.-->Price negotiation failed.Because the assumed price is too low(The estimate of the manufacturing cost of the chassis was higher than expected).

*Creating the final version for mass production and running its operation test.-->Implementation is complete and completion of the initial operation test.

Plan for coming weeks

*Execution of the final version operation test for mass production ->Start of detailed exam.

*Creation of extended I/O PCB plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->Ongoing(Start of mechanical design).


Other site works

Safety


Discussion

Plan for the coming months


Oct. - Nov. 2017

Type-A

Type-B

Type-Bp


Dec. 2017 - Mar. 2018

Type-A

Type-B


Travel Plans

Next meeting

On 2017/9/29(Fri)