Agenda/Minutes of the VIS Meeting on 2017/10/13
2017/10/13 13:30 -
Participants:
Progress report
Schedule Chart
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
Plan for coming weeks
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Other site works
- BS duct connection: Oct 2 - 6
- End of Aug. to Nov.: Mozumi entrance will be closed
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Plan for the coming months
Travel Plans
- Travel (Week of 10/16):
- Takahashi: ??
- Okutomi: 16 - 20
- Sato: ??
- Ishizaki: ??
- Mark:
- Fabian: 16 - 20
- Hirata: 16- 20
- Enzo: 16- 20
- Shoda:
- Ohishi:
- Fujii: 16 - 20
- Tanaka:
- Kozu (ICRR): 16 - 20
- Arai (ICRR): 16 - 20
- Travel (Week of 10/23):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2017/10/20(Fri)