Line 105: Line 105:
 * Temperature sensors
===
Temperature sensors ===
Line 110: Line 111:

=== Broken SRM TF blades ===
 * Check the blades for the ITM TFs if they have similar problems (Takahashi)
 * Check the BS TF blades when the next we open the BS chamber (Mark)
 * Send the broken blades to Virgo for inspection (Takahashi)
 *

Agenda/Minutes of the VIS Meeting on 2018/1/19

2018/1/19 13:30 - 14:45

Participants: Sato, Ishizaki, Takahashi, Ohishi, Aso, Mark, Enzo, Fabian, Okutomi, Tanaka, Shoda, Hirata

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF,MPP)

Type-A (Takahashi)

Past week report

[Y-end]

  • Connected the PT100 sensor for BF to the monitor system for CRY.
  • Checked the yaw rotation in BF. No problem.

[X-front]

  • Installed the main items (footholds, workbench, chairs, tools, etc.) into the clean booth.
  • Attached the release sensors onto the end plate for DP with cabling.
  • Started the assembly of side stopper. The parts for slider had a problem (too tight).

[SRM]

  • Took out the IP and TF from each box.
  • Found the blades (2 of 3) for TF were broken (completely cut off). The blades were removed.
  • Combined the IP and the TF. Connected the IP legs with the TF plate.
  • Cabled the vertical LVDT coils.
  • Fixed the upper plate of LVDT-Actuator units onto the TF plate.
  • Assembled the fishing rod of TF with cabling.
  • Assembled the yaw rotary of receptacle in the TF.
  • Packed the PI into the box.

Plan for coming weeks

  • The evacuation of EYV chamber will be started in the 23th morning.
  • Pre-assembly of BF damper.
  • Assembly of DP stage.

Type B (Mark)

Report for week of 1/15

  • We set up the QPD for the OL, initialized the OL and TM sections of the RTM, and did TFs from the TM OSEMs to the OL.
  • Initially we had no coherence, but we debugged issues with the watchdog, LPCD, and DAC board and then got good TFs.
  • We lifted the IM/RM/SR with the load gauge adapter and checked the weight, which was close to the mass budget.
  • We installed the section of the AF above the IM, and the BF cross bars and jacks, and craned in the BF.
  • We installed the BF-IRM rods, IRM, BF-IM rod, flying saucer and the cable clamps on the bottom of the BF.
  • We hooked the IM section, but found it was heavy by several hundred grams. We also noticed the BF keystone had a noticeable tilt of about 1.2 mm (high on the +X side).
  • We removed 738 g of trim mass and found that load rose and sat about 2 mm high. So the discrepancy is of order 500-600 g.
  • Shoda-san, Enzo and Kozu-kun made and characterized a batch of OSEMs.
  • Hirata-san finished drawings for the improved BS PI yaw/vertical adjustment, placed orders for damping ring receptacles and other items, and prepared the second SR BF in case we needed to swap it in.

Plan for week of 1/22

  • Fix or swap BF.
  • Route selected cables to flange.
  • Test IM picos and BF yaw pico.

Plan for week of 1/29

  • Enzo at Mitaka 1/29 and most of 1/30, then vacation.
  • Kozu-kun away.
  • All others at Kamioka.
  • Build IRM around IM.
  • Cable/test/adjust IM OSEMs.
  • Time permitting, do TFs from IM OSEMs to themselves and to optical sensor.

Vacation Info

  • Enzo 1/30-2/19 (at Mitaka 1/29, part of 1/30)
  • Kozu-kun 1/29-2/2

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

  • Hanging jig parts arrived from FCL. Some minor problems need to be fixed. Drawings will be delivered today.
  • Visited machine shop of Toyama Univ. Asked them to make some mechanical parts.
  • Made a parts list and checked the status. Will update from time to time.

  • Vertical vibration isolation bellows.
    • Firstly contacted with Mirapro but they cannot make the ones we are now using. I'll contact with NIPPON VALQUA INDUSTRIES, LTD.
  • Mirror status
    • OMMTs will arrive soon. OSTM will be ordered next FY. Perhaps need half a year.

Plan for coming weeks

  • Check hanging jig drawings.
  • Assemble the hanging jig.
  • Resume OSEM test.

Watchdog system (Tanaka)

Past week report

Plan for coming weeks

Other site works

  • Jan. 25: Monthly inspection of the cranes (11:30 - 12:30)
  • Feb 18: Black out of the Mozumi buildings

Safety

  • Incidents: no incident
  • Foreseen risks
    • Type-A: Crane
    • Type-B: Crane
    • Type-Bp: None

Discussion

Temperature sensors

  • PR2, SR2 installed
  • PR3, PRM are not yet installed. Currently put in the front room.
  • BS sensor needs to be moved to the chamber
  • VIS team will do the maintenance (battery change) of those sensors

Broken SRM TF blades

  • Check the blades for the ITM TFs if they have similar problems (Takahashi)
  • Check the BS TF blades when the next we open the BS chamber (Mark)
  • Send the broken blades to Virgo for inspection (Takahashi)

Travel Plans

  • Travel (Week of 1/22):
    • Takahashi: 22 - 26
    • Okutomi: 22 - 26
    • Sato: 23 - 26
    • Ishizaki: 23 - 26
    • Mark: 22 - 26
    • Fabian: 22 - 26
    • Hirata: 25 - 26
    • Enzo: 22 - 26
    • Shoda: 22 - 26
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR): 22 - 26
    • Arai (ICRR): 22
  • Travel (Week of 1/29):
    • Takahashi: 29 - 2
    • Okutomi: 29 - 2
    • Sato: 29 - 2
    • Ishizaki: 30 - 1
    • Mark: 29 - 2
    • Fabian: 29 - 2
    • Hirata: 29 - 2
    • Enzo:
    • Shoda: 29 - 2
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2018/1/26(Fri)