Size: 2144
Comment:
|
Size: 2285
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 30: | Line 30: |
* Hanging jig parts arrived from FCL. Brought into clean booth. Screws ordered. * Visited machine shop of Toyama Univ. Asked some mechanical parts. * Made a [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0076/E1807672/003/OMMT_parts_status2018Jan19.pdf|parts list]]. Update the status from time to time. * Contacted with Mirapro about vertical vibration isolation bellows. They cannot make the same ones we are now using. |
* Hanging jig parts arrived from FCL. Some minor problems need to be fixed. Drawings will be delivered today. * Visited machine shop of Toyama Univ. Asked them to make some mechanical parts. * Made a [[https://gwdoc.icrr.u-tokyo.ac.jp/DocDB/0076/E1807672/003/OMMT_parts_status2018Jan19.pdf|parts list]] and checked the status. Will update from time to time. * Vertical vibration isolation bellows. Firstly contacted with Mirapro but they cannot make the ones we are now using. |
Line 37: | Line 37: |
OMMTs will be arrive soon. OSTM will be ordered next FY. Perhaps need half a year. | OMMTs will arrive soon. OSTM will be ordered next FY. Perhaps need half a year. |
Line 40: | Line 40: |
* | * Check hanging jig drawings. * Assemble the hanging jig. * Resume OSEM test. |
Agenda/Minutes of the VIS Meeting on 2018/1/19
2018/1/19 13:30 -
Participants:
Progress report
Schedule Chart
Type-A : (PDF/MPP)
- Type-A:
- Type-B:
Type-A (Takahashi)
Past week report
Plan for coming weeks
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
- Hanging jig parts arrived from FCL. Some minor problems need to be fixed. Drawings will be delivered today.
- Visited machine shop of Toyama Univ. Asked them to make some mechanical parts.
Made a parts list and checked the status. Will update from time to time.
- Vertical vibration isolation bellows.
- Firstly contacted with Mirapro but they cannot make the ones we are now using. I'll contact with NIPPON VALQUA INDUSTRIES, LTD.
- Mirror status
- OMMTs will arrive soon. OSTM will be ordered next FY. Perhaps need half a year.
Plan for coming weeks
- Check hanging jig drawings.
- Assemble the hanging jig.
- Resume OSEM test.
Watchdog system (Tanaka)
Past week report
Plan for coming weeks
Other site works
- Jan. 25: Monthly inspection of the cranes (11:30 - 12:30)
- Feb 18: Black out of the Mozumi buildings
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
- Temperature sensors
Travel Plans
- Travel (Week of 1/22):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 1/29):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2018/1/26(Fri)