Line 18: Line 18:

[X-front]
  * Assembled the side stoppers for DP and BF.
  * Assembled the LVDT coils for BF damper. The primary coils were attached on the cup.
  * Measured the weight of BF (105 kg).
  * Put the BF base onto the end plate and hooked the test wire to the receptacle.
  * Tuned the BF with additional compression (load 190.4kg, frequency 0.3Hz).
  * Checked the range of FR in the BF. The range was larger than the movable limit of keystone.
  * Checked the blades on TFs. There were not any cracks on the surface of the blades.

[Y-end]
  * Release the support jack for the top chamber. The height of chamber was decreased by 2mm.
  * Removed the NIM chassis from the rack.
Line 19: Line 33:
  * Open the top chamber and the cross tube.
  * Install the DP and the BF into the chamber.

Agenda/Minutes of the VIS Meeting on 2018/2/2

2018/2/2 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:

Type-A (Takahashi)

Past week report

[X-front]

  • Assembled the side stoppers for DP and BF.
  • Assembled the LVDT coils for BF damper. The primary coils were attached on the cup.
  • Measured the weight of BF (105 kg).
  • Put the BF base onto the end plate and hooked the test wire to the receptacle.
  • Tuned the BF with additional compression (load 190.4kg, frequency 0.3Hz).
  • Checked the range of FR in the BF. The range was larger than the movable limit of keystone.
  • Checked the blades on TFs. There were not any cracks on the surface of the blades.

[Y-end]

  • Release the support jack for the top chamber. The height of chamber was decreased by 2mm.
  • Removed the NIM chassis from the rack.

Plan for coming weeks

  • Open the top chamber and the cross tube.
  • Install the DP and the BF into the chamber.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

*Preparation for assembly of mass products. --> Ongoing.

*Adjustment and approval to vendors(Meeting on machine design etc). --> Completed.

Plan for coming weeks

*Preparation for assembly of mass products.

*Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.).

Other site works

  • Feb 18: Black out of the Mozumi buildings

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

  • Fragile blades

Travel Plans

  • Travel (Week of 2/5):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 2/12):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2018/2/9(Fri)