==== Past week report ====
==== Plan for coming weeks ====
==== Report for week of 2/19 ====
 * We did TFs from the IM OSEMs.
 * We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
 * We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
 * Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
 * We added the AF crossbars and the section of the SS below the SF and craned in the SF.
 * We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.
Line 47: Line 52:
==== Plan for week of 2/26 ====
 * Shoda-san at Mitaka.
 * -
 * Enzo at Mitaka Mon 2/26.
 * '''Remove LBB temporary ballast masses from BS chamber.'''
 * Route cables up to under SF.
 * Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
 * Cable and calibrate SF LVDT.
 * Add Cu segments to SF cap.
 * Install cap.
 * Lift SF/... section and check total mass and balance.

==== Plan for week of 3/5 ====
 * Shoda-san at Mitaka.
 * Hirata-san vacation Mon 3/5, then Kamioka
 * Others at Kamioka.
 * -
 * Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
 * SR3 rack setup.
 * Other tasks TBD.

==== Plan for week of 3/12 ====
 * Shoda-san at Mitaka.
 * Mark at ASJ (Chiba) Fri 3/16.
 * Hirata-san vacation Mon 3/5, then Kamioka

==== Plan for week of 3/19 ====
 * Mark at LVC meeting
 * Shoda-san, Fabian at Mitaka

==== Plan for week of 3/26 ====
 * Mark vacation.
 * Others ???

==== To-Do Lists, Schedule ====
 * [[KAGRA/Subgroups/VIS/TypeB/March2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/April2018]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoBS]]
 * [[KAGRA/Subgroups/VIS/TypeB/ToDoSR]]
 * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=7779|JGW-L1807779-v1 Type B Schedule (SR)]]

==== Vacation Info ====
 * Enzo Mitaka day 2/26
 * Hirata-san vacation 3/5
 * Hirata-san vacation Mon 3/5
 * Fabian 3/26-4/27 vacation (then gone).

Agenda/Minutes of the VIS Meeting on 2018/2/16

2018/2/23 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

[X-front]

  • Attached the additional FR blade to the BF.
  • Needed some try and errors due to some problems (low Q, FR range, height of blade).
  • Tuned the BF again. Optimal load was 197.1kg at 0.31Hz. The FR range was 7.5mm.
  • Closed the cap of BF.
  • Extended the EQ stop to the F3 stage.
  • Lifted down the DP into the corrugate tube.
  • Set the F3 onto the end plate. maraging wire was hooked to the receptacles.
  • Tuned the F3 to 0.31Hz initially.
  • The optimal load was changed by closing the cap and hunging the F3.
  • Finally the frequency was 0.27Hz reducing the weight by 0.4kg.
  • Checked the range of FR in F3. It was 13.5mm.
  • Calibrated the LVDT in F3.
  • Started cabling between the BF and the F3.

Plan for coming weeks

[Next week]

  • Finish the cabling between the BF and the F3.
  • Lift down the BF into the corrugate tube.
  • Go to the F2 stage.

[Week of March 5]

  • Vent the EXV chamber on 5th.
  • Remove the IXV DP on 6th.
  • Insert the maraging wire for Cryo-payload with cables.

Type B (Mark)

Report for week of 2/19

  • We did TFs from the IM OSEMs.
  • We secured the cables inside the BF, added the cap and anchored the cables from below the BF to the cap.
  • We lifted the BF/... section with the load gauge adapter and measured the weight, which was about as expected.
  • Based on the measured weight, Fabian prepared an 800 g set of masses for the top of the BF.
  • We added the AF crossbars and the section of the SS below the SF and craned in the SF.
  • We installed the SF-BF rod and flying saucer and suspended the BF/... section. With the 800 g placed temporarily on the BF, the SF keystone floated at about mid-range.

Plan for week of 2/26

  • Shoda-san at Mitaka.
  • -
  • Enzo at Mitaka Mon 2/26.
  • Remove LBB temporary ballast masses from BS chamber.

  • Route cables up to under SF.
  • Check/adjust total mass and balance of BF/... section, especially IM OSEMs.
  • Cable and calibrate SF LVDT.
  • Add Cu segments to SF cap.
  • Install cap.
  • Lift SF/... section and check total mass and balance.

Plan for week of 3/5

  • Shoda-san at Mitaka.
  • Hirata-san vacation Mon 3/5, then Kamioka
  • Others at Kamioka.
  • -
  • Get SRM tank mushroom section installed (Hirata-san, Kimura-san)
  • SR3 rack setup.
  • Other tasks TBD.

Plan for week of 3/12

  • Shoda-san at Mitaka.
  • Mark at ASJ (Chiba) Fri 3/16.
  • Hirata-san vacation Mon 3/5, then Kamioka

Plan for week of 3/19

  • Mark at LVC meeting
  • Shoda-san, Fabian at Mitaka

Plan for week of 3/26

  • Mark vacation.
  • Others ???

To-Do Lists, Schedule

Vacation Info

  • Enzo Mitaka day 2/26
  • Hirata-san vacation 3/5
  • Hirata-san vacation Mon 3/5
  • Fabian 3/26-4/27 vacation (then gone).

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

  • OSEM test
  • Removed a magnet from OSEM and measured response.
    • It seemed that PD or LED inside OSEM has weak magnetic feature.

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Preparation for assembly of mass products.-->Ongoing.

  • Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)-->

    • There is no delivery.-->Contacting the vendor.

Plan for coming weeks

  • Preparation for assembly of mass products.
  • Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)

Other site works

  • 2/26 - 3/9 Construction of the walls to isolate the arms better (for cleanliness)
  • 3/12 - 3/16 Installation of the control systems for the large GVs
  • 3/12 - Center area: preparation for pump down: connecting ducts.

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

  • Center area pump down
  • PR2/3 height adjustment

Travel Plans

  • Travel (Week of 2/26):
    • Takahashi: 26 -2
    • Okutomi: 26 -2
    • Sato: 26 -1
    • Ishizaki: 26 -1
    • Mark: 26 -2
    • Fabian: 26 -2
    • Hirata:26 -2

    • Enzo:27 -2

    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR): 26 -2
    • Arai (ICRR):
  • Travel (Week of 3/5):
    • Takahashi: 5 - 9
    • Okutomi: 5 - 9
    • Sato: 5 - 9
    • Ishizaki: 5 - 9
    • Mark: 5 - 9
    • Fabian: 5 - 9
    • Hirata: 6 - 9
    • Enzo: 5 - 9
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR): 5 - 9
    • Arai (ICRR):

Next meeting

On 2018/3/2(Fri)

VIS Meeting in Mitaka: 3/16