Line 31: Line 31:
 *Preparation for assembly of mass products.-->Ongoing.
      *Programming and Unit Testing(59 Items)-->Completed( 30 of 60 Items).
  

 *Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)-->
      *Delivered(30 of 60 substrates).
      *There are two casings yet(Adjusting with vendor)-->Next week.
Line 32: Line 40:
 *Preparation for assembly of mass products.-->
      *Programming and Unit Testing(30 Items)
      *Other necessary preparations.

 *Adjustment and approval to vendors(Negotiating to guarantee machining delay of cases).-->Ongoing.

Agenda/Minutes of the VIS Meeting on 2018/3/9

2018/3/9 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Preparation for assembly of mass products.-->Ongoing.

    • Programming and Unit Testing(59 Items)-->Completed( 30 of 60 Items).

  • Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)-->

    • Delivered(30 of 60 substrates).
    • There are two casings yet(Adjusting with vendor)-->Next week.

Plan for coming weeks

  • Preparation for assembly of mass products.-->

    • Programming and Unit Testing(30 Items)
    • Other necessary preparations.
  • Adjustment and approval to vendors(Negotiating to guarantee machining delay of cases).-->Ongoing.

Other site works

  • 3/12 - 3/16 Installation of the control systems for the large GVs
  • 3/12 - Center area: preparation for pump down: connecting ducts.

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Travel Plans

  • Travel (Week of 3/12):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 3/19):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2018/3/16(Fri) in Mitaka