Line 15: Line 15:

[X-front]
  * Tested the FRs for BF and F3.
  * Measured the transfer functions of BF and F3.
  * Lifted down the EQ stop into the corrugate tube. The end plate for F3 was sit on the frame lock.
  * Assembled the end plate for F2 (release sensors, side stoppers).
  * Extended the EQ stop to the F2 stage.
  * Cabled the LVDT-Actuator and the FR for F2.
  * Installed the F2 to the EQ stop and connected to the F3 by the wire.
  * Calibrated the LVDT in F2.

[X-end]
  * Opened the top chamber and the cross tube.
  * Fixed the IP and the TF.
  * Moved the geophones form the DP.
  * Dismounted the DP.
  * Let out the cables for Cryo-payload (CP) through the shield pipe.
  * Installed the suspension wire for CP.
  * Fixed the cables on the wire.
Line 16: Line 36:

[X-front]
  * Tune the F2.
  * Cable between the F3 and the F2.
  * Go to the F1 stage.

[X-end]
  * 3/20: Wire connection with CP.
  * 3/21: Cable connection with CP.

Agenda/Minutes of the VIS Meeting on 2018/3/9

2018/3/9 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

[X-front]

  • Tested the FRs for BF and F3.
  • Measured the transfer functions of BF and F3.
  • Lifted down the EQ stop into the corrugate tube. The end plate for F3 was sit on the frame lock.
  • Assembled the end plate for F2 (release sensors, side stoppers).
  • Extended the EQ stop to the F2 stage.
  • Cabled the LVDT-Actuator and the FR for F2.
  • Installed the F2 to the EQ stop and connected to the F3 by the wire.
  • Calibrated the LVDT in F2.

[X-end]

  • Opened the top chamber and the cross tube.
  • Fixed the IP and the TF.
  • Moved the geophones form the DP.
  • Dismounted the DP.
  • Let out the cables for Cryo-payload (CP) through the shield pipe.
  • Installed the suspension wire for CP.
  • Fixed the cables on the wire.

Plan for coming weeks

[X-front]

  • Tune the F2.
  • Cable between the F3 and the F2.
  • Go to the F1 stage.

[X-end]

  • 3/20: Wire connection with CP.
  • 3/21: Cable connection with CP.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Preparation for assembly of mass products.-->Ongoing.

    • Programming and Unit Testing(59 Items)-->Completed( 30 of 60 Items).

  • Adjustment and approval to vendors(Implementation adjustments and approvals for circuit boards.)-->

    • Delivered(30 of 60 substrates).
    • There are two casings yet(Adjusting with vendor)-->Next week.

Plan for coming weeks

  • Preparation for assembly of mass products.-->

    • Programming and Unit Testing(30 Items)
    • Other necessary preparations.
  • Adjustment and approval to vendors(Negotiating to guarantee machining delay of cases).-->Ongoing.

Other site works

  • 3/12 - 3/16 Installation of the control systems for the large GVs
  • 3/12 - Center area: preparation for pump down: connecting ducts.

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Travel Plans

  • Travel (Week of 3/12):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 3/19):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2018/3/16(Fri) in Mitaka

KAGRA/Subgroups/VIS/VISMinutes20180309 (last edited 2018-03-09 16:33:32 by YoichiAso)