(after 14th May)

[X-front]
  * Swaped the IP. The wrong IP (for SR) was removed and packed.
  * Installed the right IP into the clean booth and combined it with the TF. One threaded hole to fix the IP leg was not good, but repaired by tapping.
  * Installed the PI into the top chamber.
  * Cabled from the PI to the feedthroughs.
  * Calibrated the horizontal LVDSs for the IP.
  * Put the ballast rings and three ACC units on the IP.
  * Adjusted the horizontal position of IP, the vertical position of TF, and the yaw position of BF damper.
  * Measured the spectrum of IP by the LVDT. The lowest mode frequency was 50mHz.
  * Attached the LVDT coils onto the BF and the support ring. Confirmed the signals with the driver.
  * Checked the keystone height of F1-F3. Added the ballast mass of 276g on the BF.
  * Fastened the screws for the feedthrough flanges.
  * Cabled for the ACCs.
  * The PEEK gender changer used on the ACC unit was flip connector like the feedthrough. The pre-amplifier in the ACC2 unit was broken. Swapped it to the other one,
  * Checked the signals of ACC1-3 using the new cables. They worked.
  * Attached the adjustment screw for the yaw rotation of receptacle in the TF.
  * Closed the top chamber. The installation of Type-A tower was finished except control part.
 
[Y-front]
  * Started the preparation of the site.
  * Cleaned the booth. Set the SUS sheets on the floor. Transported some items.

[Maraging blade]
  * The cutting of 26 blades was finished and delivered on 21th.
  * The aging was finished and delivered today (25th).
  * The 12 blades will be coated in the next week.
 
Line 16: Line 46:
  * Transport the DP from the X-end.
  * Start the assembly of DP and BF damper.

Agenda/Minutes of the VIS Meeting on 2018/5/25

2018/5/25 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF/MPP)

Type-B: (PDF/MPP)

Type-A (Takahashi)

Past week report

(after 14th May)

[X-front]

  • Swaped the IP. The wrong IP (for SR) was removed and packed.
  • Installed the right IP into the clean booth and combined it with the TF. One threaded hole to fix the IP leg was not good, but repaired by tapping.
  • Installed the PI into the top chamber.
  • Cabled from the PI to the feedthroughs.
  • Calibrated the horizontal LVDSs for the IP.
  • Put the ballast rings and three ACC units on the IP.
  • Adjusted the horizontal position of IP, the vertical position of TF, and the yaw position of BF damper.
  • Measured the spectrum of IP by the LVDT. The lowest mode frequency was 50mHz.
  • Attached the LVDT coils onto the BF and the support ring. Confirmed the signals with the driver.
  • Checked the keystone height of F1-F3. Added the ballast mass of 276g on the BF.
  • Fastened the screws for the feedthrough flanges.
  • Cabled for the ACCs.
  • The PEEK gender changer used on the ACC unit was flip connector like the feedthrough. The pre-amplifier in the ACC2 unit was broken. Swapped it to the other one,
  • Checked the signals of ACC1-3 using the new cables. They worked.
  • Attached the adjustment screw for the yaw rotation of receptacle in the TF.
  • Closed the top chamber. The installation of Type-A tower was finished except control part.

[Y-front]

  • Started the preparation of the site.
  • Cleaned the booth. Set the SUS sheets on the floor. Transported some items.

[Maraging blade]

  • The cutting of 26 blades was finished and delivered on 21th.
  • The aging was finished and delivered today (25th).
  • The 12 blades will be coated in the next week.

Plan for coming weeks

  • Transport the DP from the X-end.
  • Start the assembly of DP and BF damper.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

LVDT Driver (Tanaka)

Past week report

Plan for coming weeks

  • I'm working on designing and researching them.

Other site works

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Travel Plans

  • Travel (Week of 5/28):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanioka:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 6/4):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanioka:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2018/6/1(Fri)