Agenda/Minutes of the VIS Meeting on 2018/5/25
2018/5/25 13:30 - 14:30
Participants: Mark, Hirata, Sato, Takahashi, Aso, Ishizaki, Okutomi, Tanioka, Arai, Kozu, Tanaka, Enzo, Shoda, Fujii, Eleonora, Matteo
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-A (Takahashi)
Past week report
(after 14th May)
[X-front]
- Swapped the IP. The wrong IP (for SR) was removed and packed.
- Installed the right IP into the clean booth and combined it with the TF. One threaded hole to fix the IP leg was not good, but repaired by tapping.
- Installed the PI into the top chamber.
- Cabled from the PI to the feedthroughs.
- Calibrated the horizontal LVDSs for the IP.
- Put the ballast rings and three ACC units on the IP.
- Adjusted the horizontal position of IP, the vertical position of TF, and the yaw position of BF damper.
- Measured the spectrum of IP by the LVDT. The lowest mode frequency was 50mHz.
- Attached the LVDT coils onto the BF and the support ring. Confirmed the signals with the driver.
- Checked the keystone height of F1-F3. Added the ballast mass of 276g on the BF.
- Fastened the screws for the feedthrough flanges.
- Cabled for the ACCs.
- The PEEK gender changer used on the ACC unit was flip connector like the feedthrough. The pre-amplifier in the ACC2 unit was broken.
- Checked the signals of ACC1-3 using the new cables. They worked.
- Attached the adjustment screw for the yaw rotation of receptacle in the TF.
- Closed the top chamber. The installation of Type-A tower was finished except control part.
[Y-front]
- Started the preparation of the site.
- Cleaned the booth. Set the SUS sheets on the floor. Transported some items.
[Maraging blade]
- The cutting of 26 blades was finished and delivered on 21th.
- The aging was finished and delivered today (25th).
- The 12 blades will be coated in the next week.
Plan for coming weeks
- Transport the DP from the X-end to the Y-front.
- Start the assembly of DP and BF damper in Y-front.
Type B (Mark)
Report for weeks of 5/14, 5/21
- We set up for the F0 blade prototype test.
- Takahashi-san characterized the F0 prototype blades, and ordered final blades based on the BS and SR mass budgets.
- Hirata-san characterized the LBB blades and identified three sets with blades of similar strength, plus two weaker ones. However he realized that M12x50 Bumax screws for the blade sets had not been ordered, so he got a new quote and ordered them for delivery 6/11.
- Mirapro installed the mushroom section of the SRM tank.
- We added the budgeted amount of ballast to the IM/... section of the SR3.
- We craned in the BF and cabled and tested the yaw pico, the FR stepper and the LVDT.
- We hung the IM/... section from the BF, removed ≈200 g of trim mass and rearranged the rest to get the desired height, pitch and roll.
- We added the sides of the IRM and the IM OSEMs, cabled the OSEMs, and adjusted everything to get good lateral and in/out alignment of the OSEMs.
- Enzo did TFs using the IM OSEMs and the BF LVDT.
- We added the BF cap and weighed the BF/... section. We will need to remove the cap again and add about 5 kg of ballast mass.
- Hirata-san organized getting the LBB damper rings into the SR3 tank. He joined the halves of the Cu and magnet rings and got them ready for craning (which will happen later when we have rebuilt the SR3 IP and have somewhere to park the lid of the vacuum chamber). However he encountered a problem with the top ring: one of the screw holes in the top of the tank is not fully threaded, so one of the pillars supporting the top ring cannot be attached. He is considering various options.
- Hirata-san and Kozu-kun made rod assemblies for the LBB damper rings.
- Enzo made a batch of flipping and non-flipping feedthrough adapters.
- Yamamoto-san connected up the SRM rack.
- We installed a booth thermometer for the SR3.
- LBB ballast masses are ordered. Will be delivered by 6/23.
- SRM 2D drawing is in preparation.
Plan for week of 5/28
- Mark, Enzo at Kamioka Mon-Fri.
- Hirata-san at Kamioka Tue-Fri. (Mon is monthly Mitaka day.)
- Fujii-kun at Kamioka Tue-Fri.
- Matteo at Kamioka from Tue. He may help Type B to get experience.
- Kozu-kun at Kamioka Mon only. (Rest of week is job interviews.)
- --
- Hirata-san will modify and clean some Promec masses at Mitaka (making threaded holes unthreaded to allow stacking).
- Cable and test BF cap picos.
- Install internal ballast masses.
- Install cap ballast masses.
- Build up security structure to SF level.
- Crane in SF and remove cap.
- Hook BF and adjust total ballast.
- Route cables through SF-BF flying saucer up to bottom of SF.
- Adjust BF trim mass.
- Finish four half-assembled geophones.
Plan for week of 6/4
- Mark, Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri. (Mon is NAOJ medical checkup.)
- --
- Readjust payload.
- Take TFs.
- Add budgeted ballast mass to SF.
- Cable, test SF LVDT and FR.
- Characterize final F0 blades.
Plan for week of 6/11
- Mark Enzo, Hirata-san, Kozu-kun at Kamioka Tue-Fri (Mon is compensation day for f2f.)
- --
- Rebuild F0 #3 for SR3.
- Park F0 #1 (for SR2) in top of SR3 assembly frame.
- Move F0 #3 behind SR3.
- Make LBB blade sets (or at least 3 of 9).
To-Do Lists, Schedule
Vacation Info
- Mark, Enzo, Hirata-san 6/11 (comp day for f2f)
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
LVDT Driver (Tanaka)
Past week report
- The problem of P 0 was found to be due to a failure of U 25 (THAT 1646).
- I replaced the U25 and completed the repair.
- I could not confirm the problem of P3 being noisy in this environment.
- It is necessary to check again in KAGRA side.
Report on failure diagnosis and repair of LVDT driver (JGW-E1808252)PDF
Plan for coming weeks
- I'm working on designing and researching them.
Other site works
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Type-A ACCs
- Planning to use ACCs with built-in pre-amplifier for the ITM Type-A.
- One pre-amp board was broken. Need to fix it.
- One ACC is mechanically broken.
- Mechanical part is the same as the old ACCs without pre-amps.
- Transplant the pre-amp, sensors to an old one.
- These works will be done by Takahashi-san in July when we have more manpower.
High power coil drivers for Type-B
- For in-air alignment work, using high power coil drivers for the TM/IM of Type-B is necessary.
- We need to 12 more high power coil drivers for this.
- Aso will contact AEL about this.
Travel Plans
- Travel (Week of 5/28):
- Takahashi: 5/28 - 6/1
- Okutomi:
- Sato: 5/28 - 6/1
- Ishizaki:
- Mark: 5/28 - 6/1
- Hirata: 5/29 - 6/1
- Enzo: 5/28 - 6/1
- Shoda:
- Ohishi:
- Fujii: 5/29 - 6/1
- Tanioka: 5/29 - 6/1
- Tanaka:
- Kozu (ICRR): 5/28
- Arai (ICRR): 5/28 - 6/1
- Eleonora: 5/29 - 6/1
- Matteo: 5/29 - 5/31
- Travel (Week of 6/4):
- Takahashi: 5 - 8
- Okutomi:
- Sato: 5 - 8
- Ishizaki:
- Mark: 5 - 8
- Hirata: 5 - 8
- Enzo: 5 - 8
- Shoda:
- Ohishi:
- Fujii:
- Tanioka: 5 - 8
- Tanaka:
- Kozu (ICRR): 5 - 8
- Arai (ICRR):
Next meeting
On 2018/6/1(Fri)