Size: 2896
Comment:
|
Size: 3019
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 82: | Line 82: |
* Hatoya-san's summer student project * Will work on the damping of SR3 * A kick-off meeting on Monday next week |
Agenda/Minutes of the VIS Meeting on 2018/8/3
2018/8/3 13:30 - 14:30
Participants: Sato, Hatoya, Aso, Okutomi, Shoda, Ishizaki, Lucia, Hirata, Terrence, Panwei, Fujii, Mark, Fabian, Enzo
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
- 2 weeks delay for SR2
- 1 week delay for SRM
Type-A (Takahashi)
Past week report
[IYV]
1.Assembling Pre-isolator
We prepared for pre-isolator installation.
- Magnetic damper ring was placed on F1.
- EQ-Stop structure was extended to the top ring.
- We installed bridge frame on the scaffoldings.
- We combined IP and TF.
We replaced the top filter blades.
- In order to replace the blades,we removed all blades from TF.
- We bent 6 new blades and attached it to the Top Filter.
We attached the following equipment to the PI.
- Connectors, Auxiliary blade (for F1 FR), Fishing Rod for TF. But FR was not completed due to lack of parts (Parts should be present but not found.)
2.Installing Pre-isolator
- We put the pre-isolator on the bridge frame and hanged F1 or less.
Result of hanging F1 or less
- Height of TF keystone: 1mm
- Height of F1 from EQ-plate: 67.5, 79, 80
- Distance between bottom of IP and Top-ring: 5mm (initial 8mm)
TF is able to lift F1 or less.
3.Calibration of the LVDTs for BF damper.
- ---
Plan for coming weeks
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
- Sept 10(Mon): Planned power outage
Safety
- Incidents: no incident
- Foreseen risks
- Type-A: Crane work
- Type-B: Work at heights
Discussion
- Hatoya-san's summer student project
- Will work on the damping of SR3
- A kick-off meeting on Monday next week
Travel Plans
- Travel (Week of 8/6):
- Takahashi: 6 - 10
- Okutomi: 8-10
- Sato: 6 - 9
- Lucia: 6-10
- Ishizaki:
- Mark: 6-10
- Hirata: 6-10
Enzo:6-10
- Terrence: 6-10
- Shoda:
- Ohishi:
- Fujii: 6-9
- Tanioka:
- Tanaka:
- Kozu (ICRR): 6-10
- Arai (ICRR):
- Travel (Week of 8/13): KAGRA site will be closed on 8/13 and 8/14
- Takahashi: 15-17
- Okutomi:
- Sato:
- Lucia: 15-17
- Ishizaki:
- Mark:
- Hirata:
- Enzo: 15-17
- Terrence: 15-17
- Shoda:
- Ohishi:
- Fujii: 15-17
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2018/8/10(Fri)