[Y-end] * Tied the cables into a bundle around the wire. * Attached the secondary coils for the BF damper. * Dismounted the ACCs from the IP. * The cryo-payload (CP) was installed into the cryostat and the wire was connected to the CP. * Adjusted the weight of CP for the optimal load of BF. * Adjusted the height of TF keystone. [X-front] * Added the ballast ring of 19mm on the IP. * Adjusted the yaw position of the BF damper by rotating the receptacle in TF. * Released the IP and adjusted the horizontal position. * Adjusted the height of BF keystone by the FR. * Aligned the TM by the yaw picomotor in the BF. * Started the evacuation of chamber on 10th. |
|
Line 20: | Line 37: |
[Y-end] * Assembly of the geophone pods and installation. |
Agenda/Minutes of the VIS Meeting on 2018/10/12
2018/10/12 13:30 -
Participants:
Progress report
Schedule Chart
Type-A : (PDF/MPP)
Type-B: (PDF/MPP)
Type-C: (XLSX)
Type-A (Takahashi)
Past week report
[Y-end]
- Tied the cables into a bundle around the wire.
- Attached the secondary coils for the BF damper.
- Dismounted the ACCs from the IP.
- The cryo-payload (CP) was installed into the cryostat and the wire was connected to the CP.
- Adjusted the weight of CP for the optimal load of BF.
- Adjusted the height of TF keystone.
[X-front]
- Added the ballast ring of 19mm on the IP.
- Adjusted the yaw position of the BF damper by rotating the receptacle in TF.
- Released the IP and adjusted the horizontal position.
- Adjusted the height of BF keystone by the FR.
- Aligned the TM by the yaw picomotor in the BF.
- Started the evacuation of chamber on 10th.
Plan for coming weeks
[Y-end]
- Assembly of the geophone pods and installation.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
OMMT & OSTM (Ohishi)
Past week report
Plan for coming weeks
VIS electronics (Tanaka)
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
Discussion
Travel Plans
- Travel (Week of 10/15):
- Takahashi:
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
- Travel (Week of 10/22):
- Takahashi:
- Okutomi:
- Sato:
- Lucia:
- Fabian:
- Mark:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanioka:
- Tanaka:
- Kozu (ICRR):
- Arai (ICRR):
Next meeting
On 2018/10/19(Fri)