Agenda/Minutes of the VIS Meeting on 2019/9/27
2019/9/27 14:00 -
Participants:
Progress report
Type-A
Past week report
Plan for coming weeks
Type B
Past week report
Plan for coming weeks
Type-Bp
Past week report
Plan for coming weeks
OMMT & OSTM (Takahashi)
Past week report
- Evaluating the M2052 sample bar for OMC.
Plan for coming weeks
Schedule was revised (pdf/mpp).
- Go to assembly and test of the OSTM suspension using the dummy mirror in 15-18th October.
VIS electronics
Past week report
Plan for coming weeks
Other site works
Safety
- Incidents:
Discussion
- Continued discussion on the VIS repair/upgrade work between O3 and O4
Travel Plans
- Travel (Week of 9/30):
- Takahashi: 10/3-4
- Sato:
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
- Travel (Week of 10/7):
- Takahashi:
- Sato:
- Hirata:
- Shoda:
- Fujii:
- Tanaka:
Next meeting
On 2019/10/11(Fri)