Agenda/Minutes of the VIS Meeting on 2020/4/10

2020/4/10 14:00 -

Zoom Meeting

Participants:

VIS Commissioning Task List

Post-O3 task list

Schedule afetr O3

Progress report

Type-A

Past week report

Plan for coming weeks

Type B

Past week report

Plan for coming weeks

Type-Bp

Past week report

  • Assembled and tested the mirror rehanging jig.

Plan for coming weeks

Type-C

Past week report

Plan for coming weeks

VIS electronics

Past week report

Plan for coming weeks

Safety

Discussion

Travel Plans

Next meeting

On 2020/4/17(Fri)

KAGRA/Subgroups/VIS/VISMinutes20200410 (last edited 2020-04-10 14:49:23 by NaoatsuHirata)