Agenda/Minutes of the VIS Meeting on 2020/4/10
2020/4/10 14:00 - 14:40
Participants: Takahashi, Sato, Hirata, Ishizaki, Shoda, Tanaka, Aso, Fabian, Lucia
Progress report
Type-A
Past week report
Revising the Type-A installation procedure. (Takahashi)
Uploaded the mechanical assembly procedure for TF FR (Yaw and Vertical) with limit switch.Link to doc (Sato)
Plan for coming weeks
Type B
Past week report
Plan for coming weeks
Type-Bp
Past week report
Assembled and tested the mirror rehanging jig. Link to photo(Hirata)
Plan for coming weeks
Type-C
Past week report
Plan for coming weeks
VIS electronics
Past week report
- Considered if the board for additional filters can fit the remain space in the combiner box. It is difficult. (Tanaka)
- We should go to remake the board including original filter, additional filter, and pin assignment changer.
Plan for coming weeks
Safety
Discussion
Travel Plans
Next meeting
On 2020/4/17(Fri)