Agenda/Minutes of the VIS Meeting on 2020/4/10
2020/4/10 14:00 -
Participants:
Progress report
Type-A
Past week report
Revising the Type-A installation procedure.
Uploaded the mechanical assembly procedure for TF FR (Yaw and Vertical) with limit switch.Link to doc
Plan for coming weeks
Type B
Past week report
Plan for coming weeks
Type-Bp
Past week report
- Assembled and tested the mirror rehanging jig.
Plan for coming weeks
Type-C
Past week report
Plan for coming weeks
VIS electronics
Past week report
Plan for coming weeks
Safety
Discussion
Travel Plans
Next meeting
On 2020/4/17(Fri)