2020/4/10 14:00 - 2020/4/10 14:00 - 14:40
Line 6: Line 6:
Participants: Participants: Takahashi, Sato, Hirata, Ishizaki, Shoda, Tanaka, Aso, Fabian, Lucia
Line 14: Line 14:
[[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan for the long OR brake]]
Line 17: Line 19:
 * Revising the [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5500|Type-A installation procedure]].
 * Uploaded the mechanical assembly procedure for TF FR (Yaw and Vertical) with limit switch.[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11598|Link to doc]]
 * Revising the [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5500|Type-A installation procedure]]. (Takahashi)
 * Uploaded the mechanical assembly procedure for TF FR (Yaw and Vertical) with limit switch.[[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11598|Link to doc]] (Sato)
Line 25: Line 27:
 * Assembled and tested the mirror rehanging jig.  * Assembled and tested the mirror rehanging jig. [[https://photos.app.goo.gl/ftN3KENeMYQFtku99|Link to photo]](Hirata)
Line 32: Line 34:
 * Considered if the board for additional filters can fit the remain space in the combiner box. It is difficult. (Tanaka)
 * We should go to remake the board including original filter, additional filter, and pin assignment changer.

Agenda/Minutes of the VIS Meeting on 2020/4/10

2020/4/10 14:00 - 14:40

Zoom Meeting

Participants: Takahashi, Sato, Hirata, Ishizaki, Shoda, Tanaka, Aso, Fabian, Lucia

VIS Commissioning Task List

Post-O3 task list

Schedule afetr O3

Plan for the long OR brake

Progress report

Type-A

Past week report

Plan for coming weeks

Type B

Past week report

Plan for coming weeks

Type-Bp

Past week report

  • Assembled and tested the mirror rehanging jig. Link to photo(Hirata)

Plan for coming weeks

Type-C

Past week report

Plan for coming weeks

VIS electronics

Past week report

  • Considered if the board for additional filters can fit the remain space in the combiner box. It is difficult. (Tanaka)
  • We should go to remake the board including original filter, additional filter, and pin assignment changer.

Plan for coming weeks

Safety

Discussion

Travel Plans

Next meeting

On 2020/4/17(Fri)