Revision 9 as of 2020-05-22 15:35:26
Size: 660
Comment:
Revision 10 as of 2020-05-22 15:53:51
Size: 3048
Comment:
Deletions are marked like this. Additions are marked like this.
Line 8: Line 8:
[[https://www.dropbox.com/s/60oygtwmckmdyj6/Towards%20O4%20on%20VIS%20.xlsx?dl=0|Task list towards O4]] [[https://onedrive.live.com/view.aspx?resid=8E8081C20FE5EC3A!2278&ithint=file,xlsx&authkey=!AMFNtNa-Y6CVp94|Task list towards O4]]
Line 16: Line 16:
 * After a verbal report from Lucia last week I checked the condition of SR2: the control system couldn't bring the IP to its set point (klog entry [[http://klog.icr  * After a verbal report from Lucia last week I checked the condition of SR2: the control system couldn't bring the IP to its set point (klog entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14381|14381]]).
  * On Monday Lucia and I came to the site.
  * We realized coil-magnet actuation didn't move the IP but horizontal fishing rods did, so we suspected the electronics or cabling.
  * With Yamamoto-kun we went to the tunnel and realized the HPCD had broken down (entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14394|14394]]).
  * Thanks to Tomura-san's quick reaction we got a new HPCD and recovered the IP and the suspension (entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14395|14395]]).
  * I don't know what's the origin of the failure. It wasn't an actuation overload due to an earthquake because there was no earthquake (entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14407|14407]]).
  * A similar event happened to the BS IP on the 5th of May (entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14404|14404]]).
 * I have been measuring decay times of the SR2 suspension on Thursday and Friday from the control room (klog entry [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=14413|14413]]). There are no final results to show yet.
 * I asked a few elementary questions about inertial damping (questions [[https://www.dropbox.com/s/g1q38sgbgocthbu/Inertial_damping_questions_fabian.pdf?dl=0|here]]). Thank you very much Takahashi-san and Terrence for their answers! :D

=== Type-Bp ===
=== Type-C ===
 * Making the 3D model of IMMT2 suspension.

=== Controls ===
 * Summarizing the GUARDIANs.

=== Electronics ===
 * Ordered the parts for test and prepare for the test.

== Post O3 ==
 * KAGRA is in the suspended mode until 31st May.
 * Only measurements, which can be done remotely, are available ([[https://docs.google.com/spreadsheets/d/1w4q8OvX9E6nkYSgshLYLoZH5yvQXHvGmL1agux8ztx0/edit?usp=sharing|Request]]).
 * O3c is still under discussion between LVK ([[https://paper.dropbox.com/doc/Plan-for-the-long-OR-brake--AxxlJFvK1IGJjqrG5nfdHfGXAQ-KqexeqMaCA7DITFGxA5ih|Plan]], [[https://www.dropbox.com/s/hoadb73fdyah02c/Post-O3%20task.xlsx?dl=0|Sheet]]).

== Safety ==
== Discussion ==
 * Submission to JPS/ASJ Meeting.
  * JPS Meeting: 14-17 Sep. Online, Deadline: 4 Jun.
  * ASJ Meeting: 8-10 Sep. Online, Deadline: 9 Jun.
 * Report "KAGRA observation run: performance of the Type A suspensions" (Check the attached file in kagra-seis).

== Travel Plans ==
== Next meeting ==
 * On 2020/5/29(Fri)

Agenda/Minutes of the VIS Meeting on 2020/5/22

2020/5/22 14:00 - 15:20

Zoom Meeting

Participants: Takahashi, Hirata, Fabian, Miyo, Sato, Shoda, Aso, Lucia, Tanaka

Task list towards O4

Schedule afetr O3

Progress report

General

Type-A

Type-B

  • After a verbal report from Lucia last week I checked the condition of SR2: the control system couldn't bring the IP to its set point (klog entry 14381).

    • On Monday Lucia and I came to the site.
    • We realized coil-magnet actuation didn't move the IP but horizontal fishing rods did, so we suspected the electronics or cabling.
    • With Yamamoto-kun we went to the tunnel and realized the HPCD had broken down (entry 14394).

    • Thanks to Tomura-san's quick reaction we got a new HPCD and recovered the IP and the suspension (entry 14395).

    • I don't know what's the origin of the failure. It wasn't an actuation overload due to an earthquake because there was no earthquake (entry 14407).

    • A similar event happened to the BS IP on the 5th of May (entry 14404).

  • I have been measuring decay times of the SR2 suspension on Thursday and Friday from the control room (klog entry 14413). There are no final results to show yet.

  • I asked a few elementary questions about inertial damping (questions here). Thank you very much Takahashi-san and Terrence for their answers! :D

Type-Bp

Type-C

  • Making the 3D model of IMMT2 suspension.

Controls

  • Summarizing the GUARDIANs.

Electronics

  • Ordered the parts for test and prepare for the test.

Post O3

  • KAGRA is in the suspended mode until 31st May.
  • Only measurements, which can be done remotely, are available (Request).

  • O3c is still under discussion between LVK (Plan, Sheet).

Safety

Discussion

  • Submission to JPS/ASJ Meeting.
    • JPS Meeting: 14-17 Sep. Online, Deadline: 4 Jun.
    • ASJ Meeting: 8-10 Sep. Online, Deadline: 9 Jun.
  • Report "KAGRA observation run: performance of the Type A suspensions" (Check the attached file in kagra-seis).

Travel Plans

Next meeting

  • On 2020/5/29(Fri)