Agenda/Minutes of the VIS Meeting on 2020/9/4

2020/9/4 14:00 -

Zoom Meeting

Participants:

Progress report

General

Type-A

Type-B

  • IP fixing jig (Design)

  • Fabian wrote a humble plan for assessing the SRM BF condition. The document with procedures has been updated: link.

  • I'm almost finished with the corrections of the paper.
  • Next week I aim to go to the site to do some preparation work if possible.

Type-Bp

Type-C

[no progress]

Controls

Electronics

Towards O4

cf. Post Obs. task (Request), Task for O3c (Plan, Sheet), Task towards O4 (List)

Safety

Discussion

  • [Terrence] New features for the suspensions, type-A and type-B, as pre-O4 upgrades (III).

Travel Plans

Next meeting

  • On 2020/9/11(Fri)

KAGRA/Subgroups/VIS/VISMinutes20200904 (last edited 2020-09-04 16:21:25 by RyutaroTakahashi)