Size: 2133
Comment:
|
Size: 3423
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 5: | Line 5: |
13:30- | 13:40-14:10 |
Line 7: | Line 7: |
Participants: | Participants: Takahashi, Ohashi, Shoda, Hagiwara, Hirata, Ikeda, Miyo, Sato, Oshio, Ushiba, Kimura, Akutsu, Aso, Miyoki |
Line 11: | Line 11: |
* 11/2: Opening the chambers (top and cross tube), Fixing the IP and filters, Disconnection of the cables. 11/3: Disconnection of the cryo-payload. * MN oplev table design |
|
Line 13: | Line 15: |
14:00- | 14:10-15:00 |
Line 15: | Line 17: |
Participants: | Participants: Takahashi, Shoda, Ishizaki, Fabian, Hitrata, Iguchi, Miyo, Tanaka, Sato, Sugiyama, Terrence, Aso |
Line 20: | Line 22: |
* Clean-up of the IXV and IYV area. |
|
Line 21: | Line 25: |
* Clean-up of the BS and SR area. * Hirata-san asked for a quotation for 3 Top Filter keystone plates (for BS, SR3 and SR3 in case it's needed). * Fabian made progress in writing a document about LVDT card recovery. One more working day is needed. * We lost Hirose-san's lamps for checking cleanliness of mirrors. We'll keep looking for them. * We lost the medium capacity scale we used for ballast mass measurement. We need to buy one. I borrowed Miyoki-san's for a few days but he wants it back. |
|
Line 25: | Line 35: |
* Confirmation of exchange cables function in the new combiner. * Only two channels are available in the 1U chassis. |
|
Line 32: | Line 44: |
* Turn-off for the power outage. Type-A/C: Takahashi, Type-B: Fabian, Type-Bp: Miyo | |
Line 46: | Line 59: |
[Terrence] Very short introduction to VISHack [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=12125 | Slides]] |
Agenda/Minutes on 2020/10/9
CRY+VIS Interface Meeting
13:40-14:10
Participants: Takahashi, Ohashi, Shoda, Hagiwara, Hirata, Ikeda, Miyo, Sato, Oshio, Ushiba, Kimura, Akutsu, Aso, Miyoki
- Schedule on ETMY.
- 11/2: Opening the chambers (top and cross tube), Fixing the IP and filters, Disconnection of the cables. 11/3: Disconnection of the cryo-payload.
- MN oplev table design
VIS Meeting
14:10-15:00
Participants: Takahashi, Shoda, Ishizaki, Fabian, Hitrata, Iguchi, Miyo, Tanaka, Sato, Sugiyama, Terrence, Aso
Progress report
General
Type-A
- Clean-up of the IXV and IYV area.
Type-B
- Clean-up of the BS and SR area.
- Hirata-san asked for a quotation for 3 Top Filter keystone plates (for BS, SR3 and SR3 in case it's needed).
- Fabian made progress in writing a document about LVDT card recovery. One more working day is needed.
- We lost Hirose-san's lamps for checking cleanliness of mirrors. We'll keep looking for them.
- We lost the medium capacity scale we used for ballast mass measurement. We need to buy one. I borrowed Miyoki-san's for a few days but he wants it back.
Type-Bp
Type-C
Controls
Electronics
- Confirmation of exchange cables function in the new combiner.
- Only two channels are available in the 1U chassis.
Towards O4
- RSE Trial was extended to Oct. 12th.
- Preparation work was started.
- Turn-off for the power outage. Type-A/C: Takahashi, Type-B: Fabian, Type-Bp: Miyo
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
[Terrence] Very short introduction to VISHack Slides
Travel Plans
The week from 10/12
- Takahashi: 10/12-16
- Sato: 10/12-16
- Hirata: 10/12-16
The week from 10/19
- Takahashi: 10/19-10/23
Next meeting
- On 2020/10/16(Fri)