Agenda/Minutes on 2020/10/23
CRY+VIS Interface Meeting
13:30-14:00
Participants:
- Schedule of safe mode switching for WAB
- Schedule of the wire disconnection: EY 11/3, IX 11/26, EX 11/27
- Schedule of the FC painting.
- PF actuator
IP monitoring improvement in vacuum pumping -> auto-tracking system
VIS Meeting
14:00-
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
- (sato)No progress
Controls
Electronics
Towards O4
- Chamber opening will be started from Oct. 26.
- Preparation work is on going.
- Monitoring for vent. Date: 19(EY), 21(IX, IY, EY), 22(IX, IY, EY, Center). Charge: Miyo, Ikeda, Fabian
- New guardian test on 19 in PR2 and BS.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 10/26
- Hirata: 10/26-30
The week from 11/2
- Takahashi: 11/1-6
- Sato: 11/1-6
- Hirata: 11/1-6
Next meeting
- On 2020/10/30(Fri)