Agenda/Minutes on 2020/11/13
CRY+VIS Interface Meeting
13:30-14:00
Participants:
- Disassembly of the Type-A tower was finished in Y-end (11/11).
- Schedule: Wire disconnection (IX 11/13, EX 11/19), Chamber evacuation (IY 11/20).
- Jig for the FC painting.
PF actuator: Measurement of coefficients --> calculation of the noise (by mid Dec.).
VIS Meeting
14:00-
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
- [Sato](no progress)
Controls
Electronics
Towards O4
- Type-B remedy work will be started on 11/16.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 11/16
- Takahashi: 11/16-20
- Sato: 11/16-20
- Hirata: 11/16-20
The week from 11/23
- Aso: 11/24-27
- Takahashi: 11/24-27
- Hirata: 11/24-27
- Sato: ?
Next meeting
- On 2020/11/20(Fri)