Agenda/Minutes on 2021/1/22
CRY+VIS Interface Meeting
13:30-
Participants:
- Schedule for IX: Connection of ITMX is scheduled on 2/9.
- Schedule for IY: Cooling of payload is scheduled from 1/12.
- Schedule for EX: Connection of ETMX is available after 3/2.
- Corrugate tube fixing jig: Re-measurement at the beginning of March in IYV is planed.
- Commissioning in vacuum:
- Acceptance check items:
- Jig for FC painting: Under manufacturing.
- PF actuator: by the end of January.
VIS Meeting
14:00-
Participants:
Progress report
General
Type-A
- Installation in EYV.
- Opened the top chamber. The cone bellows have been broken.
- Assembled the DP and hung it from the BF.
- Calibrated the LVDT for the BF.
- Tuned the BF.
- Installed the EQ stop for BF-DP to the chamber.
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B remedy work is on going.
- Installation of Type-A was started in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 1/18
- Sato: 1/18-22
- Yano: 1/18-22
The week from 1/25
- Takahashi: 1/25-29
- Sato: 1/25-29
- Hirata: 1/25-29
- Yano: 1/25-29
Next meeting
- On 2020/1/22(Fri)