Activities in this week
Friday
15864, VIS/IX, takafumi.ushiba, Comment to Cabling for cryo-payload (Click here to view original report: 15860)
15866, VIS/IX, ryutaro.takahashi, Comment to Cabling for cryo-payload (Click here to view original report: 15860)
Sunday
15868, VIS/General, kouseki.miyo, Some suspensions are not SAFE.
15869, VIS/PR3, fabian.arellano, Comment to Gluing the mirror wire. (Click here to view original report: 15844)
15871, VIS/General, kouseki.miyo, ISOLATED state is available with only LVDTs not blended sensors.
Monday
15872, VIS/OMM, ryutaro.takahashi, Comment to Modification of ACCs (Click here to view original report: 15617)
15873, VIS/General, kouseki.miyo, Comment to Relay Switch of Stepper Motor Driver (Click here to view original report: 15847)
15875, VIS/PR3, fabian.arellano, Comment to Gluing the mirror wire. (Click here to view original report: 15844)
15876, VIS/PR2, satoru.ikeda, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
15877, VIS/General, satoru.ikeda, Comment to We investigated the network connection. (Click here to view original report: 15737)
15878, CRY/Cryo-payload EX, takafumi.ushiba, EX payload upgrade
Tuesday
15880, VIS/PR2, satoru.ikeda, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
15881, PEM/Center, takaaki.yokozawa, IXC
15882, VIS/PR2, satoru.ikeda, Comment to The PR2-SF's stepper motor has stalled. (Click here to view original report: 15857)
15883, CRY/Cryostat IY, takayuki.tomaru, IYC test (temperature & frosting)
15884, CRY/Cryostat IY, rishabh.bajpai, Vibration Analysis
15886, VIS/PR3, satoru.ikeda, Driveable range of the PR3 GAS SF stepper motor
15888, VIS/General, kouseki.miyo, All payload models are in PAYLOAD_MASTER.mdl
15885, VIS/PR3, fabian.arellano, Comment to Gluing the mirror wire. (Click here to view original report: 15844)
15889, VIS/PR3, fabian.arellano, Traverser motor test and cabling.
15890, VIS/PR3, satoru.ikeda, Comment to Traverser motor test and cabling. (Click here to view original report: 15889)
15891, VIS/EY, ryutaro.takahashi, Setup of F3
Wednesday
15893, VIS/EY, kouseki.miyo, Comment to Setup of F3 (Click here to view original report: 15891)
15894, VIS/EY, kouseki.miyo, Comment to Setup of F3 (Click here to view original report: 15891)
15905, PEM/General, tatsuki.washimi, Bird watching (Ondotori maintenance) 2021
15906, VIS/EY, kouseki.miyo, Comment to Setup of F3 (Click here to view original report: 15891)
15908, CRY/Cryo-payload EX, takafumi.ushiba, Comment to EX payload upgrade (Click here to view original report: 15878)
15911, VIS/PR3, satoru.ikeda, Comment to Traverser motor test and cabling. (Click here to view original report: 15889)
15910, VIS/EY, kouseki.miyo, TF measurement for F3 GAS filter
15912, VIS/EY, kouseki.miyo, Comment to Setup of F3 (Click here to view original report: 15891)
15913, CRY/Cryostat IY, takayuki.tomaru, IYC cooler no.3
15916, IOO/IMC, tomotada.akutsu, Pre-inspection of the suspension structures for MCi
15917, IOO/IMC, tomotada.akutsu, Turned off the power supply to the tilt-sensor laser
15918, VIS/EY, ryutaro.takahashi, Comment to Setup of F3 (Click here to view original report: 15891)
15919, VIS/EY, ryutaro.takahashi, Setup of BF
15920, VIS/PR3, satoru.ikeda, Comment to Traverser motor test and cabling. (Click here to view original report: 15889)
15921, VIS/SR3, fabian.arellano, Oplev installation.
Agenda/Minutes on 2021/2/5
CRY+VIS Interface Meeting
13:30-
Participants:
Copy from previous meeting
- Schedule for IX: Connection is scheduled in the week of 2/8. Do you work on 2/11?
- Schedule for IY: Disconnection is scheduled on 3/11.
- Schedule for EX: Connection is scheduled in the week of 3/15.
- Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
- Commissioning in vacuum: Two phased commissioning will be tried in IX at beginning. After that, one phase is default.
- Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
- Jig for FC painting: Under manufacturing.
- PF actuator: by the end of January.
VIS Meeting
14:00-
Participants:
Progress report
General
Type-A
- Finished assembly of the ACCs and the geophone pods in IX.
- Setup the F3: Calibration of the LVDT, Measurement of the FR range, Tuning of filter, Measurement of the TFs, Cabling around the F3.
- Lifted down the EQ stop into the corrugate tube. The F3 stage sit down the frame lock.
Type-B
Type-Bp
Type-C
- Remedy of cabling for the actuator coils in the IMC suspensions is required.
Controls
Electronics
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 2/8
- Takahashi: 2/8-12
- Sato: 2/8-12
- Hirata: 2/8-12
- Yano: 2/8-12
The week from 2/15
- Takahashi: 2/15-19
- Sato: 2/15-19
- Hirata: 2/15-19
- Yano: 2/15-19
Next meeting
- On 2020/2/12(Fri)