Line 2: Line 2:

= Activities in this week =
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15617|15617]], VIS/OMM, ryutaro.takahashi: Modification of ACCs
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15872|15872]], VIS/OMM, ryutaro.takahashi: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15684|15684]], VIS/SR2, satoru.ikeda: Support for common Payload model files: Payload of Type-B (SR2) is supported to PAYLOAD_MASTER.
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15937|15937]], VIS/SR2, kouseki.miyo: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15737|15737]], VIS/General, satoru.ikeda: We investigated the network connection.
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15877|15877]], VIS/General, satoru.ikeda: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15844|15844]], VIS/PR3, fabian.arellano: Gluing the mirror wire.
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15875|15875]], VIS/PR3, fabian.arellano: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15885|15885]], VIS/PR3, fabian.arellano: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15941|15941]], VIS/PR3, fabian.arellano: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15847|15847]], VIS/General, satoru.ikeda: Relay Switch of Stepper Motor Driver
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15873|15873]], VIS/General, kouseki.miyo: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15857|15857]], VIS/PR2, satoru.ikeda: The PR2-SF's stepper motor has stalled.
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15876|15876]], VIS/PR2, satoru.ikeda: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15880|15880]], VIS/PR2, satoru.ikeda: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15882|15882]], VIS/PR2, satoru.ikeda: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15868|15868]], VIS/General, kouseki.miyo: Some suspensions are not SAFE.
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15923|15923]], VIS/General, kouseki.miyo: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15889|15889]], VIS/PR3, fabian.arellano: Traverser motor test and cabling.
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15920|15920]], VIS/PR3, satoru.ikeda: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15944|15944]], VIS/PR3, satoru.ikeda: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15890|15890]], VIS/PR3, satoru.ikeda: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15911|15911]], VIS/PR3, satoru.ikeda: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15891|15891]], VIS/EY, ryutaro.takahashi: Setup of F3
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15912|15912]], VIS/EY, kouseki.miyo: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15918|15918]], VIS/EY, ryutaro.takahashi: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15894|15894]], VIS/EY, kouseki.miyo: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15893|15893]], VIS/EY, kouseki.miyo: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15906|15906]], VIS/EY, kouseki.miyo: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15919|15919]], VIS/EY, ryutaro.takahashi: Setup of BF
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15926|15926]], VIS/EY, kouseki.miyo: Comment
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15931|15931]], VIS/EY, ryutaro.takahashi: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15928|15928]], VIS/SR3, fabian.arellano: Oplev installation and alignment recovery.
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15935|15935]], VIS/SR3, kouseki.miyo: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15932|15932]], VIS/EY, ryutaro.takahashi: Setup of F3
 - [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15936|15936]], VIS/EY, kouseki.miyo: Comment
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15886|15886]], VIS/PR3, satoru.ikeda: Driveable range of the PR3 GAS SF stepper motor
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15888|15888]], VIS/General, kouseki.miyo: All payload models are in PAYLOAD_MASTER.mdl
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15889|15889]], VIS/PR3, fabian.arellano: Traverser motor test and cabling.
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15891|15891]], VIS/EY, ryutaro.takahashi: Setup of F3
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15910|15910]], VIS/EY, kouseki.miyo: TF measurement for F3 GAS filter
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15919|15919]], VIS/EY, ryutaro.takahashi: Setup of BF
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15921|15921]], VIS/SR3, fabian.arellano: Oplev installation.
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15928|15928]], VIS/SR3, fabian.arellano: Oplev installation and alignment recovery.
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15930|15930]], VIS/PR2, satoru.ikeda: Connect and check the drive of the PR2 traverser.
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15932|15932]], VIS/EY, ryutaro.takahashi: Setup of F3
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15938|15938]], VIS/General, kouseki.miyo: Comment to Support for common model files: Installation on Type-A (ETMX, ETMY, ITMX) and Type-B (SRM, SR2) (Click here to view original report: 15641)
[[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15950|15950]], VIS/EY, ryutaro.takahashi: Setup of F2

= Agenda/Minutes on 2021/2/5 =
= Agenda/Minutes on 2021/2/12 =
Line 57: Line 6:
13:30-14:00 13:30-
Line 63: Line 12:
 * Schedule for IX: Release is scheduled on 2/18.
 * Schedule for IY: Disconnection is scheduled on 3/11.
 * Schedule for EX: Connection is scheduled in the week of 3/15.
 * Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
 * Commissioning in air:
 * Commissioning in vacuum:
 * Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
 * PF actuator: Dead line depends on the schedule of commissioning.
 * Jig for FC painting: Delivered.
Line 64: Line 23:
14:00-14:40 14:00-
Line 68: Line 27:
== Activities in this week ==
=== VIS/General ===
'''Summary''': Ikeda-san worked on following items;

(1) Measured the length of the network cable (15956) and now prepare to order the cables with DGS group.

(2) He got message from manufacturer that it is difficult to operate the picomotor for long time (more 24 hours). So he is now considering to request to AEL group to make the circuit box that turns power on and off with BIO signal like the stepper motor circuit. (15958)

(3) He made the new MEDM screen for stepper motor on MN stage which is developed by Nishimoto-kun. We can open the screen from [sitemap]/[STEPPING MOTOR]/[CRY_OVERVIEW] (15965).

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15737|15737]] We investigated the network connection. , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15956|15956]] Comment, __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15958|15958]] About Picomotor's 24-hour operation , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15965|15965]] Integration of Cryo Payload Phytron motor driver into MEDM , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15983|15983]] I posted this by mistake. , __satoru.ikeda__

=== VIS/EY ===
'''Summary''': Setup of the F2 stage in EY: installation of suspension wire, cabling, calibration of LVDT, check of FR range, tuning
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15950|15950]] Setup of F2 , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15959|15959]] Connection between F3 and F2 , __naohisa.satou__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15972|15972]] Cabling between F3 and F2 , __naohisa.satou__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15982|15982]] Setup of F2 , __ryutaro.takahashi__
 * (!) Thursday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15993|15993]] Setup of F2 , __ryutaro.takahashi__
=== VIS/IX ===
'''Summary''': Connection of the cryo-payload in IX, mounted the geophones onto the IP in IX, and compressed the F0 blades in IX.

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15968|15968]] Connection to cryo-payload , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15974|15974]] Comment, __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15968|15968]] Connection to cryo-payload , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15981|15981]] Setup of pre-isolator , __ryutaro.takahashi__

=== VIS/MCE ===
'''Summary''': Akutsu-san found the optical lever light hit on the edge of the MCE mirror during his investigation on IMC ghost beams.

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15987|15987]] MCe oplev , __tomotada.akutsu__

=== VIS/PRM ===
'''Summary''':

(1) Miyo fixed the swapped cabling on the BF-damper for PRM with Nakagaki-san, and after that, the noise coupling of the transfer function at higher frequency is decreased to the same behavior of other PR suspensions (15994).

(2) Ikeda-san touched the picomotor of PRM for his first operation (15957) before measure the calibration factor between picomotor and OSEM.

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=9449|9449]] PRM glitch investigation: , __koki.okutomi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15960|15960]] Comment, __kouseki.miyo__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15988|15988]] Comment , __kouseki.miyo__
  * (!) Thursday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15994|15994]] Comment , __kouseki.miyo__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15957|15957]] Checking the operation of PRM's Picomotor PRM_BF and PRM_IM , __satoru.ikeda__

=== VIS/PR3 ===
'''Summary''': Ikeda-san tested the picomotor operation and measured rough calibration value for PR3-IM picomotor (15977). During the test for BF picomotor, it was stucked (15976). So we need open the top chamber to fix that.

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15977|15977]] PR3 IM PITCH, ROLL, YAW's Picomotor is operated to measure the travel and drive range , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15979|15979]] Comment, __satoru.ikeda__

=== VIS/SR3 ===
'''Summary''': aaa.

 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15928|15928]] Oplev installation and alignment recovery. , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15953|15953]] Comment, __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15963|15963]] IM ballast mass adjustment , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15975|15975]] Comment, __fabian.arellano__
  * (!) Thursday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15990|15990]] Comment , __fabian.arellano__
  * (!) Thursday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15991|15991]] Comment , __fabian.arellano__
Line 70: Line 95:
 * [Miyo] See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/VISMinutes20210212#VIS.2BAC8-General|Activities/General]]
Line 71: Line 98:
 * [Takahashi] See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/VISMinutes20210212#VIS.2BAC8-EY|EY]]
 * [Takahashi] See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/VISMinutes20210212#VIS.2BAC8-IX|IX]]
Line 73: Line 102:
 * [Fabian?] See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/VISMinutes20210212#VIS.2BAC8-SR3|SR3]]
Line 75: Line 106:
 * [Miyo] See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/VISMinutes20210212#VIS.2BAC8-PR3|PR3]]
 * [Miyo] See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/VISMinutes20210212#VIS.2BAC8-PRM|PRM]]
Line 76: Line 110:
 * [Miyo] See [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/VISMinutes20210212#VIS.2BAC8-MCE|MCE]]
Line 78: Line 113:
No update.
Line 80: Line 116:
????
Line 97: Line 135:
 * [Ikeda] How to rescue the stucked picomotor named BF-T for PR3. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|klog#15976]]
 * [Miyo] When and who work on the IMC repairing? This work is not included in the [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|VIS schedule]].
 * Do you have?
Line 98: Line 140:
The week from 2/8

 * Takahashi: 2/8-12
 * Sato: 2/8-12
 * Hirata: 2/8-12
 * Yano: 2/8-12
Line 112: Line 147:
The week from 2/22

 * Takahashi: 2/23-26
 * Sato: 2/22-26
 * Hirata: 2/23-26
 * Yano: 2/22-26
Line 113: Line 155:
 * On 2020/2/12(Fri)  * On 2020/2/19(Fri)

Agenda/Minutes on 2021/2/12

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

Post O3 Upgrade portal

  • Schedule for IX: Release is scheduled on 2/18.
  • Schedule for IY: Disconnection is scheduled on 3/11.
  • Schedule for EX: Connection is scheduled in the week of 3/15.
  • Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
  • Commissioning in air:
  • Commissioning in vacuum:
  • Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
  • PF actuator: Dead line depends on the schedule of commissioning.
  • Jig for FC painting: Delivered.

VIS Meeting

14:00-

Participants:

Activities in this week

VIS/General

Summary: Ikeda-san worked on following items;

(1) Measured the length of the network cable (15956) and now prepare to order the cables with DGS group.

(2) He got message from manufacturer that it is difficult to operate the picomotor for long time (more 24 hours). So he is now considering to request to AEL group to make the circuit box that turns power on and off with BIO signal like the stepper motor circuit. (15958)

(3) He made the new MEDM screen for stepper motor on MN stage which is developed by Nishimoto-kun. We can open the screen from [sitemap]/[STEPPING MOTOR]/[CRY_OVERVIEW] (15965).

  • 15737 We investigated the network connection. , satoru.ikeda

    • 15956 Comment, satoru.ikeda

  • 15958 About Picomotor's 24-hour operation , satoru.ikeda

  • 15965 Integration of Cryo Payload Phytron motor driver into MEDM , satoru.ikeda

  • 15983 I posted this by mistake. , satoru.ikeda

VIS/EY

Summary: Setup of the F2 stage in EY: installation of suspension wire, cabling, calibration of LVDT, check of FR range, tuning

  • 15950 Setup of F2 , ryutaro.takahashi

  • 15959 Connection between F3 and F2 , naohisa.satou

  • 15972 Cabling between F3 and F2 , naohisa.satou

  • 15982 Setup of F2 , ryutaro.takahashi

  • (!) Thursday 15993 Setup of F2 , ryutaro.takahashi

VIS/IX

Summary: Connection of the cryo-payload in IX, mounted the geophones onto the IP in IX, and compressed the F0 blades in IX.

  • 15968 Connection to cryo-payload , ryutaro.takahashi

    • 15974 Comment, ryutaro.takahashi

  • 15968 Connection to cryo-payload , ryutaro.takahashi

  • 15981 Setup of pre-isolator , ryutaro.takahashi

VIS/MCE

Summary: Akutsu-san found the optical lever light hit on the edge of the MCE mirror during his investigation on IMC ghost beams.

  • 15987 MCe oplev , tomotada.akutsu

VIS/PRM

Summary:

(1) Miyo fixed the swapped cabling on the BF-damper for PRM with Nakagaki-san, and after that, the noise coupling of the transfer function at higher frequency is decreased to the same behavior of other PR suspensions (15994).

(2) Ikeda-san touched the picomotor of PRM for his first operation (15957) before measure the calibration factor between picomotor and OSEM.

  • 9449 PRM glitch investigation: , koki.okutomi

    • 15960 Comment, kouseki.miyo

    • 15988 Comment , kouseki.miyo

    • (!) Thursday 15994 Comment , kouseki.miyo

  • 15957 Checking the operation of PRM's Picomotor PRM_BF and PRM_IM , satoru.ikeda

VIS/PR3

Summary: Ikeda-san tested the picomotor operation and measured rough calibration value for PR3-IM picomotor (15977). During the test for BF picomotor, it was stucked (15976). So we need open the top chamber to fix that.

  • 15977 PR3 IM PITCH, ROLL, YAW's Picomotor is operated to measure the travel and drive range , satoru.ikeda

  • 15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda

    • 15979 Comment, satoru.ikeda

VIS/SR3

Summary: aaa.

  • 15928 Oplev installation and alignment recovery. , fabian.arellano

    • 15953 Comment, fabian.arellano

  • 15963 IM ballast mass adjustment , fabian.arellano

    • 15975 Comment, fabian.arellano

    • (!) Thursday 15990 Comment , fabian.arellano

    • (!) Thursday 15991 Comment , fabian.arellano

Progress report

General

Type-A

  • [Takahashi] See EY

  • [Takahashi] See IX

Type-B

  • [Fabian?] See SR3

Type-Bp

  • [Miyo] See PR3

  • [Miyo] See PRM

Type-C

  • [Miyo] See MCE

Controls

No update.

Electronics

????

Towards O4

Safety

Discussion

  • [Ikeda] How to rescue the stucked picomotor named BF-T for PR3. klog#15976

  • [Miyo] When and who work on the IMC repairing? This work is not included in the VIS schedule.

  • Do you have?

Travel Plans

The week from 2/15

  • Takahashi: 2/15-19
  • Sato: 2/15-19
  • Hirata: 2/15-19
  • Yano: 2/15-19

The week from 2/22

  • Takahashi: 2/23-26
  • Sato: 2/22-26
  • Hirata: 2/23-26
  • Yano: 2/22-26

Next meeting

  • On 2020/2/19(Fri)

KAGRA/Subgroups/VIS/VISMinutes20210212 (last edited 2021-02-12 21:04:59 by RyutaroTakahashi)