Contents
Activities in this week
CRY/Cryo-payload EX
CRY/Cryostat IY
IYC cooling restart (15951), takayuki.tomaru
VIS/EY
Setup of F3 (15932), ryutaro.takahashi
Comment (15936), kouseki.miyo
Setup of F2 (15950), ryutaro.takahashi
Monday Connection between F3 and F2 (15959), naohisa.satou
VIS/General
Support for common model files: Installation on Type-A (ETMX, ETMY, ITMX) and Type-B (SRM, SR2) (15641), satoru.ikeda
Comment (15938), kouseki.miyo
We investigated the network connection. (15737), satoru.ikeda
Monday Comment (15956), satoru.ikeda
Monday About Picomotor's 24-hour operation (15958), satoru.ikeda
VIS/PR3
Gluing the mirror wire. (15844), fabian.arellano
Comment (15941), fabian.arellano
Traverser motor test and cabling. (15889), fabian.arellano
Comment (15944), satoru.ikeda
VIS/PRM
PRM glitch investigation: (9449), koki.okutomi
Tuesday Comment (15960), kouseki.miyo
Monday Checking the operation of PRM's Picomotor PRM_BF and PRM_IM (15957), satoru.ikeda
VIS/SR2
Support for common Payload model files: Payload of Type-B (SR2) is supported to PAYLOAD_MASTER. (15684), satoru.ikeda
Comment (15937), kouseki.miyo
VIS/SR3
Oplev installation and alignment recovery. (15928), fabian.arellano
Agenda/Minutes on 2021/2/12
CRY+VIS Interface Meeting
13:30-14:00
Participants:
VIS Meeting
14:00-14:40
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 2/8
- Takahashi: 2/8-12
- Sato: 2/8-12
- Hirata: 2/8-12
- Yano: 2/8-12
The week from 2/15
- Takahashi: 2/15-19
- Sato: 2/15-19
- Hirata: 2/15-19
- Yano: 2/15-19
Next meeting
- On 2020/2/12(Fri)