Differences between revisions 33 and 51 (spanning 18 versions)
Revision 33 as of 2021-02-09 07:42:15
Size: 4676
Editor: KousekiMiyo
Comment:
Revision 51 as of 2021-02-12 07:29:22
Size: 6083
Editor: KousekiMiyo
Comment:
Deletions are marked like this. Additions are marked like this.
Line 4: Line 4:
'''CRY/Cryo-payload EX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15878|15878]] EX payload upgrade , __takafumi.ushiba__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15948|15948]] Comment, __takafumi.ushiba__
'''CRY/Cryostat IY'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15951|15951]] IYC cooling restart , __takayuki.tomaru__
Line 10: Line 5:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15932|15932]] Setup of F3 , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15936|15936]] Comment, __kouseki.miyo__
Line 13: Line 6:
 * (!) Monday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15959|15959]] Connection between F3 and F2 , __naohisa.satou__  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15959|15959]] Connection between F3 and F2 , __naohisa.satou__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15972|15972]] Cabling between F3 and F2 , __naohisa.satou__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15982|15982]] Setup of F2 , __ryutaro.takahashi__
 * (!) Thursday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15993|15993]] Setup of F2 , __ryutaro.takahashi__
Line 15: Line 11:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15641|15641]] Support for common model files: Installation on Type-A (ETMX, ETMY, ITMX) and Type-B (SRM, SR2) , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15938|15938]] Comment, __kouseki.miyo__
Line 18: Line 12:
  * (!) Monday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15956|15956]] Comment, __satoru.ikeda__
 * (!) Monday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15958|15958]] About Picomotor's 24-hour operation , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15956|15956]] Comment, __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15958|15958]] About Picomotor's 24-hour operation , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15965|15965]] Integration of Cryo Payload Phytron motor driver into MEDM , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15983|15983]] I posted this by mistake. , __satoru.ikeda__
'''VIS/IX'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15968|15968]] Connection to cryo-payload , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15974|15974]] Comment, __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15968|15968]] Connection to cryo-payload , __ryutaro.takahashi__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15981|15981]] Setup of pre-isolator , __ryutaro.takahashi__
'''VIS/MCE'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15987|15987]] MCe oplev , __tomotada.akutsu__
Line 21: Line 24:
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15844|15844]] Gluing the mirror wire. , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15941|15941]] Comment, __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15889|15889]] Traverser motor test and cabling. , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15944|15944]] Comment, __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15979|15979]] Comment, __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15977|15977]] PR3 IM PITCH, ROLL, YAW's Picomotor is operated to measure the travel and drive range , __satoru.ikeda__
Line 27: Line 30:
  * (!) Tuesday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15960|15960]] Comment, __kouseki.miyo__
 * (!) Monday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15957|15957]] Checking the operation of PRM's Picomotor PRM_BF and PRM_IM , __satoru.ikeda__
'''VIS/SR2'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15684|15684]] Support for common Payload model files: Payload of Type-B (SR2) is supported to PAYLOAD_MASTER. , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15937|15937]] Comment, __kouseki.miyo__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15960|15960]] Comment, __kouseki.miyo__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15988|15988]] Comment , __kouseki.miyo__
  * (!) Thursday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15994|15994]] Comment , __kouseki.miyo__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15957|15957]] Checking the operation of PRM's Picomotor PRM_BF and PRM_IM , __satoru.ikeda__
Line 34: Line 36:
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15935|15935]] Comment, __kouseki.miyo__
  * (!) Monday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15953|15953]] Comment , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15953|15953]] Comment, __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15963|15963]] IM ballast mass adjustment , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15975|15975]] Comment, __fabian.arellano__
  * (!) Thursday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15990|15990]] Comment , __fabian.arellano__
  * (!) Thursday [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15991|15991]] Comment , __fabian.arellano__
Line 41: Line 46:
13:30-14:00 13:30-
Line 47: Line 52:
 * Schedule for IX: Release is scheduled on 2/18.
 * Schedule for IY: Disconnection is scheduled on 3/11.
 * Schedule for EX: Connection is scheduled in the week of 3/15.
 * Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
 * Commissioning in air:
 * Commissioning in vacuum:
 * Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
 * PF actuator: Dead line depends on the schedule of commissioning.
 * Jig for FC painting: Delivered.
Line 48: Line 63:
14:00-14:40 14:00-
Line 55: Line 70:
 * Setup of the F2 stage in EY: installation of suspension wire, cabling, calibration of LVDT, check of FR range, tuning
 * Connection of the cryo-payload in IX.
 * Mounted the geophones onto the IP in IX.
 * Compressed the F0 blades in IX.
Line 58: Line 77:
=== Type-C ===
=== Controls ===
=== Electronics ===
Line 59: Line 81:
=== Type-C ===

=== Controls ===

=== Electronics ===
Line 81: Line 98:
 * [Ikeda] How to rescue the stucked picomotor named BF-T for PR3. [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|klog#15976]]
Line 82: Line 101:
The week from 2/8

 * Takahashi: 2/8-12
 * Sato: 2/8-12
 * Hirata: 2/8-12
 * Yano: 2/8-12
Line 96: Line 108:
The week from 2/22

 * Takahashi: 2/23-26
 * Sato: 2/22-26
 * Hirata: 2/23-26
 * Yano: 2/22-26
Line 97: Line 116:
 * On 2020/2/12(Fri)  * On 2020/2/19(Fri)

Activities in this week

VIS/EY

  • 15950 Setup of F2 , ryutaro.takahashi

  • 15959 Connection between F3 and F2 , naohisa.satou

  • 15972 Cabling between F3 and F2 , naohisa.satou

  • 15982 Setup of F2 , ryutaro.takahashi

  • (!) Thursday 15993 Setup of F2 , ryutaro.takahashi

VIS/General

  • 15737 We investigated the network connection. , satoru.ikeda

    • 15956 Comment, satoru.ikeda

  • 15958 About Picomotor's 24-hour operation , satoru.ikeda

  • 15965 Integration of Cryo Payload Phytron motor driver into MEDM , satoru.ikeda

  • 15983 I posted this by mistake. , satoru.ikeda

VIS/IX

  • 15968 Connection to cryo-payload , ryutaro.takahashi

    • 15974 Comment, ryutaro.takahashi

  • 15968 Connection to cryo-payload , ryutaro.takahashi

  • 15981 Setup of pre-isolator , ryutaro.takahashi

VIS/MCE

  • 15987 MCe oplev , tomotada.akutsu

VIS/PR3

  • 15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda

    • 15979 Comment, satoru.ikeda

  • 15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda

  • 15977 PR3 IM PITCH, ROLL, YAW's Picomotor is operated to measure the travel and drive range , satoru.ikeda

VIS/PRM

  • 9449 PRM glitch investigation: , koki.okutomi

    • 15960 Comment, kouseki.miyo

  • 15988 Comment , kouseki.miyo

    • (!) Thursday 15994 Comment , kouseki.miyo

  • 15957 Checking the operation of PRM's Picomotor PRM_BF and PRM_IM , satoru.ikeda

VIS/SR3

  • 15928 Oplev installation and alignment recovery. , fabian.arellano

    • 15953 Comment, fabian.arellano

  • 15963 IM ballast mass adjustment , fabian.arellano

    • 15975 Comment, fabian.arellano

    • (!) Thursday 15990 Comment , fabian.arellano

    • (!) Thursday 15991 Comment , fabian.arellano

Agenda/Minutes on 2021/2/12

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants:

Post O3 Upgrade portal

  • Schedule for IX: Release is scheduled on 2/18.
  • Schedule for IY: Disconnection is scheduled on 3/11.
  • Schedule for EX: Connection is scheduled in the week of 3/15.
  • Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
  • Commissioning in air:
  • Commissioning in vacuum:
  • Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
  • PF actuator: Dead line depends on the schedule of commissioning.
  • Jig for FC painting: Delivered.

VIS Meeting

14:00-

Participants:

Progress report

General

Type-A

  • Setup of the F2 stage in EY: installation of suspension wire, cabling, calibration of LVDT, check of FR range, tuning
  • Connection of the cryo-payload in IX.
  • Mounted the geophones onto the IP in IX.
  • Compressed the F0 blades in IX.

Type-B

Type-Bp

Type-C

Controls

Electronics

Towards O4

Safety

Discussion

  • [Ikeda] How to rescue the stucked picomotor named BF-T for PR3. klog#15976

Travel Plans

The week from 2/15

  • Takahashi: 2/15-19
  • Sato: 2/15-19
  • Hirata: 2/15-19
  • Yano: 2/15-19

The week from 2/22

  • Takahashi: 2/23-26
  • Sato: 2/22-26
  • Hirata: 2/23-26
  • Yano: 2/22-26

Next meeting

  • On 2020/2/19(Fri)

KAGRA/Subgroups/VIS/VISMinutes20210212 (last edited 2021-02-12 21:04:59 by RyutaroTakahashi)