* VIS/SR2, [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15684|15684]], satoru.ikeda: Support for common Payload model files: Payload of Type-B (SR2) is supported to PAYLOAD_MASTER. | * VIS/SR2, [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15684|15684]], satoru.ikeda: Support for common Payload model files: Payload of Type-B (SR2) is supported to PAYLOAD_MASTER. |
Contents
Activities in this week
VIS/SR2, 15684, satoru.ikeda: Support for common Payload model files: Payload of Type-B (SR2) is supported to PAYLOAD_MASTER.
15937, kouseki.miyo: Comment
VIS/PR3, 15844, fabian.arellano: Gluing the mirror wire.
15941, fabian.arellano: Comment
VIS/PR3, 15889, fabian.arellano: Traverser motor test and cabling.
15944, satoru.ikeda: Comment
VIS/SR3, 15928, fabian.arellano: Oplev installation and alignment recovery.
15935, kouseki.miyo: Comment
VIS/EY, 15932, ryutaro.takahashi: Setup of F3
15936, kouseki.miyo: Comment
VIS/General, 15938, kouseki.miyo: Comment to Support for common model files: Installation on Type-A (ETMX, ETMY, ITMX) and Type-B (SRM, SR2) (Click here to view original report: 15641)
VIS/EY, 15950, ryutaro.takahashi: Setup of F2
Agenda/Minutes on 2021/2/5
CRY+VIS Interface Meeting
13:30-14:00
Participants:
VIS Meeting
14:00-14:40
Participants:
Progress report
General
Type-A
Type-B
Type-Bp
Type-C
Controls
Electronics
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
Travel Plans
The week from 2/8
- Takahashi: 2/8-12
- Sato: 2/8-12
- Hirata: 2/8-12
- Yano: 2/8-12
The week from 2/15
- Takahashi: 2/15-19
- Sato: 2/15-19
- Hirata: 2/15-19
- Yano: 2/15-19
Next meeting
- On 2020/2/12(Fri)