Size: 2251
Comment:
|
Size: 6980
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 3: | Line 3: |
= Agenda/Minutes on 2021/2/12 = | = Agenda/Minutes on 2021/2/19 = |
Line 7: | Line 7: |
13:30-13:55 | 13:30- |
Line 9: | Line 9: |
Participants: | Participants: |
Line 12: | Line 13: |
* Schedule for IX: Release is scheduled on 2/18. | * Schedule for IX: Released on 2/18. BF is overload. |
Line 17: | Line 18: |
* Commissioning in vacuum: Closing of DN800 flange is available within a half of day. | * Commissioning in vacuum: |
Line 20: | Line 21: |
* Jig for FC painting: Delivered. | * Jig for FC painting: Assembling. |
Line 23: | Line 24: |
14:00-15:30 | 14:00- |
Line 28: | Line 29: |
=== Schedule === {{http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Subgroups/VIS/VISMinutes20210219?action=AttachFile&do=get&target=vis_gant_0219.png|vis_gant+0219|width=1000}} |
|
Line 29: | Line 32: |
=== Electronics === | [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|JGW-L2011475-v26]] |
Line 31: | Line 34: |
=== Control === | === General === '''General''' Summary: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15737|15737]] We investigated the network connection. , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16028|16028]] Comment, __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16038|16038]] Initialize the OSEMINF filters for all Type-Bp suspensions , __kouseki.miyo__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16040|16040]] Comment, __kouseki.miyo__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16036|16036]] Cabling for temperature control equipment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16038|16038]] Initialize the OSEMINF filters for all Type-Bp suspensions , __kouseki.miyo__ === Type-C === '''MCF''' Summary: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16041|16041]] Recovery of IMC suspension , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16049|16049]] Comment, __naohisa.satou__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16041|16041]] Recovery of IMC suspension , __ryutaro.takahashi__ === Type-A === '''EY''' Summary: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15993|15993]] Setup of F2 , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16023|16023]] Comment, __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16034|16034]] Comment , __ryutaro.takahashi__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16050|16050]] Comment , __ryutaro.takahashi__ '''IX''' Summary: * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16055|16055]] Setup of BF with the released cryo-payload , __ryutaro.takahashi__ === Type-Bp === '''PR2''' Summary: * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16054|16054]] PR2 minirack is moved to 2nd floor , __kouseki.miyo__ '''PR3''' Summary: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15889|15889]] Traverser motor test and cabling. , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16027|16027]] Comment, __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16024|16024]] Comment, __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16026|16026]] Comment , __satoru.ikeda__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16032|16032]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16043|16043]] Comment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16052|16052]] Comment , __fabian.arellano__ * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16056|16056]] Comment , __fabian.arellano__ '''PRM''' Summary: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16048|16048]] Operation check of Picomotor of PRM IM and BF , __satoru.ikeda__ === Type-B === '''SR3''' Summary: * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15963|15963]] IM ballast mass adjustment , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16009|16009]] Comment, __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16007|16007]] Ballast mass adjustment on top of BF , __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16018|16018]] Comment, __fabian.arellano__ * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16035|16035]] Comment , __fabian.arellano__ === Electronics (Tanaka-san) === === Control (Miyo) === |
Line 50: | Line 117: |
* '''When will we do the recovering work for type-Bp suspensions?''' Situations of the suspension are here; * PRM: All cables are connected except the PSD which is not use now. Miyo is checking the acceptance items; TF of the plant response, sensor noise level, calibration values, diagonalization, coil balancing, damping filter. These are not finished and are not summarized. * PR2: Cables connected but signal is not coming from the satelite box. We have to check. I can do that next week with Nakagaki-san even I have to join the IMC commissioning. * PR3: All Cables are connected. Fabian team is investigating the suspension which is touching somewhere. * '''Cabling style of the thermistors is reviewed by SEO?''' * How to extract the thermistor cables? * No conflict to other subsystems: AOS VAC? Stray light is OK? The cabling does not disturb VAC people to work when they install the bellows? * |
|
Line 52: | Line 127: |
The week from 2/22 * Takahashi: 2/23-2/28 * Sato: 2/23-26 * Hirata: 2/23-26 * Yano: 2/23-26 The week from 3/1 * Takahashi: 3/1-5 * Sato: 3/1-5 * Hirata: 3/1-5 * Yano: 3/1-5 |
|
Line 54: | Line 142: |
* On 2020/2/zz(Fri) | * On 2020/2/26(Fri) |
Contents
Agenda/Minutes on 2021/2/19
CRY+VIS Interface Meeting
13:30-
Participants:
- Schedule for IX: Released on 2/18. BF is overload.
- Schedule for IY: Disconnection is scheduled on 3/11.
- Schedule for EX: Connection is scheduled in the week of 3/15.
- Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
- Commissioning in air: Commissioning of IX will be started. Other schedule has not been decided yet.
- Commissioning in vacuum:
- Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting: Assembling.
VIS Meeting
14:00-
Participants:
Progress report
Schedule
General
General Summary:
15737 We investigated the network connection. , satoru.ikeda
16028 Comment, satoru.ikeda
16038 Initialize the OSEMINF filters for all Type-Bp suspensions , kouseki.miyo
16040 Comment, kouseki.miyo
16036 Cabling for temperature control equipment , satoru.ikeda
16038 Initialize the OSEMINF filters for all Type-Bp suspensions , kouseki.miyo
Type-C
MCF Summary:
16041 Recovery of IMC suspension , ryutaro.takahashi
16049 Comment, naohisa.satou
16041 Recovery of IMC suspension , ryutaro.takahashi
Type-A
EY Summary:
15993 Setup of F2 , ryutaro.takahashi
IX Summary:
16055 Setup of BF with the released cryo-payload , ryutaro.takahashi
Type-Bp
PR2 Summary:
16054 PR2 minirack is moved to 2nd floor , kouseki.miyo
PR3 Summary:
15889 Traverser motor test and cabling. , fabian.arellano
16027 Comment, satoru.ikeda
15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda
PRM Summary:
16048 Operation check of Picomotor of PRM IM and BF , satoru.ikeda
Type-B
SR3 Summary:
15963 IM ballast mass adjustment , fabian.arellano
16009 Comment, fabian.arellano
16007 Ballast mass adjustment on top of BF , fabian.arellano
Electronics (Tanaka-san)
Control (Miyo)
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
When will we do the recovering work for type-Bp suspensions? Situations of the suspension are here;
- PRM: All cables are connected except the PSD which is not use now. Miyo is checking the acceptance items; TF of the plant response, sensor noise level, calibration values, diagonalization, coil balancing, damping filter. These are not finished and are not summarized.
- PR2: Cables connected but signal is not coming from the satelite box. We have to check. I can do that next week with Nakagaki-san even I have to join the IMC commissioning.
- PR3: All Cables are connected. Fabian team is investigating the suspension which is touching somewhere.
Cabling style of the thermistors is reviewed by SEO?
- How to extract the thermistor cables?
- No conflict to other subsystems: AOS VAC? Stray light is OK? The cabling does not disturb VAC people to work when they install the bellows?
Travel Plans
The week from 2/22
- Takahashi: 2/23-2/28
- Sato: 2/23-26
- Hirata: 2/23-26
- Yano: 2/23-26
The week from 3/1
- Takahashi: 3/1-5
- Sato: 3/1-5
- Hirata: 3/1-5
- Yano: 3/1-5
Next meeting
- On 2020/2/26(Fri)