* '''When will we do the recovering work for type-Bp suspensions?''' Fabian team go to X end in next week even we could not complete the upgrade work on Type-Bp suspensions. Situations of the suspension are here; | * '''When will we do the recovering work for type-Bp suspensions?''' Situations of the suspension are here; |
Contents
Agenda/Minutes on 2021/2/19
CRY+VIS Interface Meeting
13:30-
Participants:
- Schedule for IX: Released on 2/18. BF is overload.
- Schedule for IY: Disconnection is scheduled on 3/11.
- Schedule for EX: Connection is scheduled in the week of 3/15.
- Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
- Commissioning in air: Commissioning of IX will be started. Other schedule has not been decided yet.
- Commissioning in vacuum:
- Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
- PF actuator: Not evaluated in IX, but after the commissioning for suspension.
- Jig for FC painting: Assembling.
VIS Meeting
14:00-
Participants:
Progress report
Schedule
General
General Summary:
15737 We investigated the network connection. , satoru.ikeda
16028 Comment, satoru.ikeda
16038 Initialize the OSEMINF filters for all Type-Bp suspensions , kouseki.miyo
16040 Comment, kouseki.miyo
16036 Cabling for temperature control equipment , satoru.ikeda
16038 Initialize the OSEMINF filters for all Type-Bp suspensions , kouseki.miyo
Type-C
MCF Summary:
16041 Recovery of IMC suspension , ryutaro.takahashi
16049 Comment, naohisa.satou
16041 Recovery of IMC suspension , ryutaro.takahashi
Type-A
EY Summary:
15993 Setup of F2 , ryutaro.takahashi
IX Summary:
16055 Setup of BF with the released cryo-payload , ryutaro.takahashi
Type-Bp
PR2 Summary:
16054 PR2 minirack is moved to 2nd floor , kouseki.miyo
PR3 Summary:
15889 Traverser motor test and cabling. , fabian.arellano
16027 Comment, satoru.ikeda
15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda
PRM Summary:
16048 Operation check of Picomotor of PRM IM and BF , satoru.ikeda
Type-B
SR3 Summary:
15963 IM ballast mass adjustment , fabian.arellano
16009 Comment, fabian.arellano
16007 Ballast mass adjustment on top of BF , fabian.arellano
Electronics (Tanaka-san)
Control (Miyo)
Towards O4
- Type-B/Bp remedy work is on going.
- Installation of Type-A is on going in EY.
- Schedule.
- Procedure documents.
- Criteria in the acceptance test.
Safety
Discussion
When will we do the recovering work for type-Bp suspensions? Situations of the suspension are here;
- PRM: All cables are connected except the PSD which is not use now. Miyo is checking the acceptance items; TF of the plant response, sensor noise level, calibration values, diagonalization, coil balancing, damping filter.
- PR2: Cables connected but signal is not coming from the satelite box. We have to check. I can do that next week with Nakagaki-san even I have to join the IMC commissioning.
- PR3: All Cables are connected. Fabian team is investigating the suspension which is touching somewhere.
Cabling style of the thermistors is reviewed by SEO?
- How to extract the thermistor cables?
- No conflict to other subsystems: AOS VAC? Stray light is OK? The cabling does not disturb VAC people to work when they install the bellows?
Travel Plans
The week from 2/22
- Takahashi: 2/23-2/28
- Sato: 2/23-26
- Hirata: 2/23-26
- Yano: 2/23-26
The week from 3/1
- Takahashi: 3/1-5
- Sato: 3/1-5
- Hirata: 3/1-5
- Yano: 3/1-5
Next meeting
- On 2020/2/26(Fri)