Agenda/Minutes
CRY+VIS Interface Meeting
Date 2021/5/7: 13:00-
Participants:
Schedule
- IX: IP will be released on 5/10. To adjust the length Oplev, damping of the filter chain is necessary.
- IY: Remedy of the pre-isolator is postponed.
EX: Height adjustment is on going (Status).
- EY: Installation of the tower will be restarted on 5/11. Removing of the maraging rod is necessary.
Status
- Corrugate tube fixing jig: Replaced for IXV. Other 3 sets are necessary by late July.
- Procedure of TM height setting: Plan for EX.
- Commissioning in air: From mid. May for IX.
- Commissioning in vacuum:
- Acceptance check: Group work is set every Friday to make the acceptance check document.
- PF actuator: After SC.
- Jig for FC painting: Test was scheduled in the week of 5/17.
Discussion