Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/6/18 13:00-
Participants:
Schedule
- IX: H4 geophone was replaced. Top chamber was closed again.
- IY: Schedule: Rough alignment of TM?
- EX: Adjustment of Yaw FR and IP tuning was finished. Broken cable was recovered. Top chamber was closed.
- EY: Assembly of payload is on going. Status of mirror cleaning?
Status
- Corrugate tube fixing jig: Delivery and implement were scheduled on 7/12-13.
- TM height setting: Next target is ITMY.
- Commissioning in air: X-arm.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check: Group work is set every Friday.
- PF actuator: After SC.
- Jig for FC painting:
- Separation of rack in 2F: On the maintenance days.
- Disassembly of PRM/PR2 assembly frame: This was scheduled on 6/28-29.
Discussion
VIS Meeting
14:00-
Participants:
Klog
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
Type-A
Type-B
Type-B
Type-Bp
TypeC
Electronics
Control
Schedule
See Schedule
- Type-A team: ACC preparation
- Type-B team: IP tuning
Milestone
IMC suspensions are ready in air [40] will finish 2021/04/21.
PRs are ready in air [643] will finish 2021/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2021/11/24.
SRs are ready in air [663] will finish 2021/12/20.
Output suspensions are ready in air [695] will finish 2021/12/21.
TMSY is ready in air [708] will finish 2021/??/??.
TMSX is ready in air [684] will finish 2021/??/??.
2021/03/29 updated
Safety
Discussion
Travel Plans
The week from 6/21
- Takahashi: 6/21-22
- Hirata: 6/21-22
- Yano: 6/21-25
The week from 6/28
- Takahashi: 6/28-7/2
- Sato: 6/28-7/2
- Hirata: 6/28-7/2
- Yano: 6/28-7/2
Next meeting
- 2021/6/25(FRI)