Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/7/9 13:00-14:00
Participants: Takahashi, Ikeda, Sato, Ushiba, Kimura, Aso, Tomaru, Node, Hirata
Schedule
- IX: To the finalization.
- EX: Alignment for the green beam was finished. To the finalization
- IY: Height adjustment is on going.
- EY: Mirror cleaning is on going in Mitaka. Measurement system had a problem. The shipping will be in the end of next week at earliest.
Status
- Corrugate tube fixing jig: Implementation is scheduled on 7/12-13.
- TM height setting: ITMY.
- Commissioning in air: X-arm.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check: Every Friday.
- PF actuator: After SC.
- Separation of rack in 2F: This is scheduled on 7/16.
- New vacuum pumps for V-chambers: Considering the port location.
- Extension of cables for picomotor drivers: Tested in EYV.
Discussion
Adjustable height range of the filter chain in IY
- The condition of F1 stepper motor is the same as the F3 in IX. We tried to move the motor with the stand alone driver, but the FR is still not working.
- The motor is still not working?
- The FR slider is stuck?
- The range of BF is too small. Check the mechanical stopper.
- Tune the F0 more to lower frequency (now 0.4Hz) in order to extend the range.
Next meeting
- 2021/7/16(FRI)
Klog
This is generated by python script in /users/Miyo/dropbox/Script/scrapping/main.py.
Summary Report
Type-A
- Adjusted the ballasts on the cryo-payload and the BF in IY. Additional spring was implemented on the BF.
- Repaired the broken cables for TF/BF actuator opening the chamber. The BF and TF were recovered and the chamber was closed.
Type-B
Type-Bp
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Adjustment of IYV
- Type-B team: MSB
Milestone
IMC suspensions are ready in air [40] will finish 2021/04/21.
PRs are ready in air [643] will finish 2021/07/09.
ETMX is ready in air [656] will finish 2021/08/25.
ITMX is ready in air [657] will finish 2021/08/31.
ETMY is ready in air [658] will finish 2021/09/16.
ITMY is ready in air [659] will finish 2021/11/08.
BS is ready in air [691] will finish 2021/11/24.
SRs are ready in air [663] will finish 2021/12/20.
Output suspensions are ready in air [695] will finish 2021/12/21.
TMSY is ready in air [708] will finish 2021/??/??.
TMSX is ready in air [684] will finish 2021/??/??.
2021/03/29 updated
Safety
Discussion
Travel Plans
The week from 7/5
- Takahashi: 7/5-8 (KIW8 7/7-9)
- Sato: 7/5-8
- Hirata: 7/5-9
- Yano: 7/5-9
The week from 7/12
- Takahashi: 7/12-16
- Sato: 7/12-16
- Hirata: 7/12-16
- Yano: 7/12-16
Next meeting
- 2021/7/16(FRI)